Skip to Main Content

Find Case LawBeta

Judgments and decisions from 2001 onwards

ABC v Barts Health NHS Trust

[2016] EWHC 500 (QB)

Case No: HQ13X05588
Neutral Citation Number: [2016] EWHC 500 (QB)
IN THE HIGH COURT OF JUSTICE
QUEEN'S BENCH DIVISION

Royal Courts of Justice

Strand, London, WC2A 2LL

Date: 11/03/2016

Before :

HIS HONOUR JUDGE MCKENNA

Between :

ABC (A protected party proceeding by his wife and litigation friend DEF)

Claimant

- and -

Barts Health NHS Trust

Defendant

Henry Witcomb QC (instructed by Tees Law Solicitors) for the Claimant

Claire Toogood (instructed by Kennedys Solicitors) for the Defendant

Hearing date: 7 March 2016

Judgment

HHJ McKenna:

Introduction

1.

In this action, the Claimant, ABC who is a protected party who brings his claim by his wife and litigation friend DEF, has pursued a claim for damages in respect of the delay on the part of the Defendant, Barts Health NHS Trust, in his treatment on 30th January 2003 at Whipps Cross Hospital after he suffered a dissection of his aorta which was not diagnosed and only identified some 20 days later on 19th February 2003 which in turn led to a surgical repair on 20th February 2003.

2.

It is the Claimant’s case that the dissection created an abnormality in his aorta – a false lumen – which due to the negligent delay between 30th January and 20th February 2003, failed to heal when, with timely surgical repair shortly after 30th January 2003 it would have healed. In addition it is said that this abnormality went on to cause a thrombus or blood clot to form in the aorta and to travel to and occlude the left middle cerebral artery causing a catastrophic infarction of his brain on 5th April 2006. It is also contended that the negligence also prevented the Claimant from undergoing renal transplantation.

3.

Breach of duty was admitted at a relatively early stage in the Defendant’s letter of response dated 21st April 2014. In particular the Defendant admitted that the aortic dissection should have been diagnosed on 30th January 2003, that successful surgical repair should have followed shortly thereafter and that there was a negligent delay in diagnosis between 30th January and 20th February 2003.

4.

Initially, however, causation of any injury, loss and damage was denied. However on 23rd April 2015 the Defendant amended paragraph 22.3(c) of its defence to admit that the admitted breach of duty caused the Claimant to suffer some injury necessitating a fasciotomy and a femoro-femoral crossover bypass graft repair (which had been carried out on 20th February 2003 at the same time as the repair to the dissection in the aorta). This surgery was necessary because the false lumen had descended to the femoral and iliac arteries on 19th February 2003 when it had not done so before that date and would not have done so with competent care. The injury is discrete and according to the Defendant only sounded in general damages for pain and suffering.

5.

The Defendant denied that its negligence resulted in the Claimant being unable to undergo renal transplantation and his suffering the extensive left-sided middle cerebral artery infarction which occurred on 5th April 2006.

6.

There were therefore a number of distinct issues in the litigation:

i)

Breach of duty and delay in surgery (which was admitted in February 2014).

ii)

The extent of the surgery in 2003 where in its amended defence, the Defendant admitted that fasciotomy and femoro-femoral crossover bypass graft would have been avoided but for the delay in surgery.

iii)

Causation and consequences of the stroke in 2006 and the Claimant’s inability to undergo renal transplantation.

It is fair to say that it is this third issue which gives rise, on the Claimant’s case, to the overwhelming majority of the claim (put at in excess of £1 million plus annual payments of in excess £230,000 in the Claimant’s schedule of loss) and in respect of which all the very extensive quantum expert evidence and therefore costs were incurred.

7.

The trial of this action was due to commence on 7th March 2016. However, on 24th February 2016 the Claimant accepted the Defendant’s Part 36 offer of £50,000 (inclusive of an interim payment of £25,000) which offer had in fact expired on 24th June 2015 (it having been made on 4th June 2015). The offer was expressed to be a settlement of the whole of the Claimant’s claim. The Claimant being a protected party pursuant to CPR 21.10 the court’s approval for the terms of settlement was necessary and on 7th March 2016 this court formally approved the terms of settlement.

8.

Unfortunately the parties were not able to agree liability for costs which therefore must be determined by this court pursuant to CPR 36.13(5) and it is to that issue that this judgment is directed.

The Law

9.

The following provisions of the CPR are relevant:

“36.13(5) Where paragraph (4)(b) applies but the parties cannot agree the liability for costs, the court must, unless it considers it unjust to do so, order that—

(a)

the claimant be awarded costs up to the date on which the relevant period expired; and

(b)

the offeree do pay the offeror’s costs for the period from the date of expiry of the relevant period to the date of acceptance.

(6)

In considering whether it would be unjust to make the orders specified in paragraph (5), the court must take into account all the circumstances of the case including the matters listed in rule 36.17(5).

36.17(5) In considering whether it would be unjust to make the orders referred to in paragraphs (3) and (4), the court must take into account all the circumstances of the case including—

(a)

the terms of any Part 36 offer;

(b)

the stage in the proceedings when any Part 36 offer was made, including in particular how long before the trial started the offer was made;

(c)

the information available to the parties at the time when the Part 36 offer was made;

(d)

the conduct of the parties with regard to the giving of or refusal to give information for the purposes of enabling the offer to be made or evaluated; and

(e)

whether the offer was a genuine attempt to settle the proceedings.”

Issue

10.

The Claimant contends that there is no good reason to depart from what I will refer to as the usual order provided for in CPR Part 36.13(5), namely the Claimant is awarded its costs up until 25th June 2015 with the Claimant paying the Defendant’s costs between 25th June 2015 and 25th February 2016. The Defendant by contrast submits that having regard to all the circumstances of the case, such an order would be unjust because it fails to reflect that the Claimant has failed in relation to the vast majority of his pleaded claim and contends for an order that the Claimant’s costs up to 25th June 2015 be limited to the issue of the femoro-femoral bypass graft (thus excluding all the causation costs) and that the Claimant should pay the Defendant’s costs relating to the causation of the stroke and the losses consequent thereon up until and including 25th June 2015 and all the Defendant’s costs of the action thereafter. The issue therefore is whether it is unjust to make the usual order and, if it is, what different order should the court make.

The Part 36 offer

11.

The material provisions of the Defendant’s offer dated 4th June 2015 which, as I have previously recorded, were expressed to be in settlement of the whole claim are as follows:

“If the Claimant accepts the Defendant’s offer by 25.06.15 the Defendant will:

(1)

Pay the £50,000 (less interim payments) (if any) within 14 days of the date of acceptance or (in cases requiring an order for payment) the date of the order for payment;

(2)

Pay to the Department for Work and Pensions (the “DWP”) recoverable benefits (if any), paid to the Claimant up to the date of this offer;

(3)

Pay to the DWP any further recoverable benefits paid to the Claimant from the date of this offer to the actual date of payment of the net amount. For avoidance of doubt the Defendant will not deduct any part of the further recoverable benefits from the net amount;

(4)

Pay the Claimant’s reasonable costs up to 25.06.15 or the date of acceptance of the Defendant’s offer, whichever is the earlier, such costs to be agreed or assessed on the standard basis in accordance with CPR Part 36.1. In addition if approval is required by the Civil Procedure Rules, the Defendant will pay the Claimant’s reasonable costs of obtaining approval of the settlement.”

Discussion and conclusion

12.

It was submitted on behalf of the Claimant that at the time the Defendant had made its offer in June 2015 the Defendant was in possession of all the relevant material and information in order properly to evaluate the claim and make an offer to settle the whole claim. It did not, as it could have done, protect its position so far as the causation costs (if I may so describe them) are concerned by framing its Part 36 offer in such a way as to exclude that issue. Having failed so to do, what it submits rhetorically has happened subsequently to render the usual order in respect of the pre-acceptance of costs (and the order which would have flowed as a matter of course if the offer had been accepted in time) unjust. Furthermore, looking at the particular factors in CPR 36.17(5) there is nothing which renders the usual order unjust. The terms of the offer provide for a settlement of the whole claim. Such a settlement envisaged that all the pre-acceptance costs (subject to detailed assessment) would be recoverable by the Claimant and there has been no new information which has come into the Defendant’s possession which might affect the position.

13.

What is said on behalf of the Defendant is that if the Claimant had simply, as it submits the Claimant should have done, brought a claim for the delay in surgery, fasciotomy and femoro-femoral crossover bypass graft none of the quantum experts would have been required. The claim would have been settled for general damages and at proportionate cost. It concedes that if the Claimant had accepted its Part 36 offer within the relevant period then the Defendant would have been liable for the whole of the Claimant’s costs to that date including the causation costs (subject to detailed assessment) but submits that by rejecting the offer the Claimant has forfeited its automatic right to the usual order as to costs so that the court has to exercise its discretion in accordance with the relevant provisions of Part 36. In so doing the court must look at all the circumstances of the case including the specific factors referred to in CPR 36.17(5) in order to determine whether it would be unjust to make the usual order and that when all the circumstances of the case are considered the court should in fact make a different order. In this case, the court can easily separate out the evidence relating to the issues in which the Claimant was successful and the issues in which the Claimant was unsuccessful and that an issue-based costs order, albeit unusual, would best meet the objective of doing justice between the parties.

14.

At the time that the Claimant made his decision to reject the Defendant’s Part 36 offer, he knew exactly what the Defendant’s case was in respect of each of the three issues and in particular in respect of causation and was aware of the Defendant’s expert evidence on the issue and why the Defendant suggested that the expert evidence relied upon by the Claimant was flawed (exchange of expert reports on causation from cardiothoracic surgeons, vascular surgeons, nephrologists and urologists having been exchanged on 30th January 2015 and the cardiac surgeons having had a joint meeting on 5th May 2015). Moreover, even after the rejection of its offer the Defendant continued to set out in correspondence why it considered the Claimant would fail on the causation issue (for example in Kennedys’ letter of 4th November 2015).

15.

Thus it was submitted that the Defendant had acted reasonably throughout in making early concessions in formulating a generous Part 36 offer and in all the circumstances it would be unjust if it were now to be placed in a worse position than it would have been had it gone to trial (a trial that was only days away when the Part 36 offer was eventually accepted by the Claimant) and won on the causation issue. Moreover, given that the Claimant had rejected the Defendant’s generous Part 36 offer the court could reasonably infer that if the Defendant had made a more restricted offer it would not have found favour with the Claimant who himself has acted unreasonably in rejecting the Defendant’s offer and causing both parties to incur very substantial additional costs only to accept the offer made in June 2015 a matter of days before trial was due to begin.

16.

It is common ground that Part 36 is a separate, self-contained code and must be applied as such as Lord Justice Ward put it in Shovelar v Lane [2012] 1 WLR 637. Moreover, the court’s discretion to depart from the usual order is constrained by the precondition that its full enforcement would be unjust. It follows, it seems to me, that the discretion is more circumscribed than the broad discretion under CPR 44.2. Moreover, the specific considerations identified in CPR 36.17(5) have this common feature that they focus analysis on the circumstances of the making of the offer, the provision or otherwise of the relevant information in relation to it rather than more general issues as to conduct although I remind myself that the requirement to take into account all the circumstances does enable the court to take a broader view and to consider the various matters relied upon by the Defendant.

17.

The difficulty with the broad thrust of the Defendant’s submissions as it seems to me is that the Defendant had the means and opportunity to protect itself in respect of the costs that it was going to have to incur in respect of the causation issue but chose for whatever reason when making its Part 36 offer to frame the offer as a settlement of the whole claim and then subsequently when that offer was not accepted did not make any revised offer excluding causation. True it is that in rejecting the offer and pursuing the action up to or close to trial the Claimant acted unreasonably but Part 36 expressly provides an effective remedy to cater for that very situation in that the Claimant will have to pay all the Defendant’s costs incurred post expiry of the Part 36 offer and in the circumstances of this case it seems to me that the assessment of those costs should be on the indemnity basis. To my mind, there is nothing unjust about making the usual order in the circumstances of this case, accepting as I do, the thrust of the Claimant’s submissions on this issue.

Disposal

18.

It follows in my judgment, subject to any submissions which the parties may wish to make as to the terms of an order to reflect the substance of this judgment, that the appropriate order in respect of costs is as follows:

i)

The Defendant do pay the Claimant’s costs up to 25th June 2015 on the standard basis to be subject to a detailed assessment if not agreed and with the Claimant’s solicitor waiving any claim to further costs.

ii)

The Claimant do pay the Defendant’s costs from 25th June 2015 to 24th February 2016 on the indemnity basis to be subject to detailed assessment if not agreed.

iii)

The Defendant do pay the Claimant’s costs from 24th February 2016 on the standard basis to be subject to a detailed assessment if not agreed and with the Claimant’s solicitor waiving any claim to further costs.

19.

I am most grateful to both counsel for their very helpful submissions on this issue.

20.

Assuming the parties are able to agree on the form of the order in which case I should be grateful if they would file a copy, there will be no need for any attendance when this judgment is formally handed down.

ABC v Barts Health NHS Trust

[2016] EWHC 500 (QB)

Download options

Download this judgment as a PDF (197.6 KB)

The original format of the judgment as handed down by the court, for printing and downloading.

Download this judgment as XML

The judgment in machine-readable LegalDocML format for developers, data scientists and researchers.