Skip to Main Content

Find case lawBeta

Judgments and decisions from 2001 onwards

QBE Management Services (UK) Ltd v Dymoke & Ors

[2012] EWHC 116 (QB)

Case No: HQ11X03120
Neutral Citation Number: [2012] EWHC 116 (QB)

IN THE HIGH COURT OF JUSTICE

QUEEN'S BENCH DIVISION

ORDER

Royal Courts of Justice

Strand, London, WC2A 2LL

Date: 2nd February 2012

Before :

MR JUSTICE HADDON-CAVE

Between :

QBE MANAGEMENT SERVICES (UK) LIMITED

Claimant

- and -

(1) CHARLES DYMOKE

(2) JOHN HEARN

(3) STEVEN KIRK

(4) PRO INSURANCE SOLUTIONS LTD

Defendants

David Reade QC and Dale Martin (instructed by Mayer Brown International LLP) for the Claimant

Selwyn Bloch QC, Damian Brown, Craig Rajgopaul-Hicklin (instructed by Morgan Lewis & Bockius LLP) for the Defendants

Hearing dates: 2nd, 3rd, 7th, 8th, 10th, 11th, 14th, 15th, 18th, 21st, 22nd, 23rd November, 21st December 2011 and 27th January 2012

Judgment

The Hon. Mr Justice Haddon-Cave:

1.

I handed down my full Judgment in this matter on 27th January 2012 in which I found for the Claimant on the main issues and granted ‘springboard’ relief until 28th April 2012, together with damages in the sum of £314,030.81.

2.

The following three consequential matters remain for determination:

(1)

The form of the final Order.

(2)

Costs.

(3)

Permission to Appeal.

(1) The form of the final Order

3.

There was a debate between the parties as to the form of the Order for final injunctive relief.

4.

The Claimant contended that the form of the Order for final injunctive relief should be the same as the Interim Order which I made on 21st December 2011 when I indicated to the parties my decision (save for the deletion of the word “own” in paragraphs 1, 3 and 5 of the Interim Order which they were content should come out).

5.

Mr Selwyn Bloch QC, Counsel for the Defendants, raised two objections to the form of the final Order. First, to the inclusion of the words “…or set up…” in paragraphs 1, 3 and 5 of the Interim Order. Second, to inclusion of paragraphs 2, 4, 6 and 7 dealing with inducing breaches of contract by others. Mr Bloch submitted that the words “…or set up…” were inappropriate and too broad for inclusion in the Order. He argued that they would exclude permissible ‘preparatory’ acts, in particular those which Mr Hearn had identified in his fifth witness statement as being steps which the Defendant wished to take in order, Mr Bloch explained, that the new venture wished to ‘hit the ground running’ on 28th April 2012. Mr Bloch QC also argued that paragraphs 2, 4, 6 and 7 should be struck out because this was an attempt by the Claimant to enforce unenforceable and open-ended restrictive covenants as to confidentiality ‘by the back door’. He said that to include them in the final Order would not be consistent with my finding that the non-compete covenants were unenforceable and, in any event, would be disproportionate in what was already a robust order.

6.

Mr David Reade QC, Counsel for the Claimant, submitted that the Defendants had not previously objected to the formulation of these paragraphs which followed the Interim Order of Mr Nigel Wilkinson QC on 18th October 2012. He said that the formulation was appropriate as final ‘springboard’ relief which should be aimed at ameliorating the consequences of the Defendants’ unlawful actions. He further argued that confidentiality was an enduring obligation which required indefinite protection in the context of this case.

7.

It was common ground that the form of the final Order is a matter of discretion for the Court.

The Principles

8.

The principles to be applied when formulating ‘springboard’ relief are, in my view, as follows:

(1)

First, the form of the Order and ‘springboard’ relief should fit the facts.

(2)

Second, the ‘springboard’ relief should reflect and restrain the spectrum of the unlawful activities which made up the ‘springboard’.

(3)

Third, in granting ‘springboard’ relief, the Court may restrain otherwise lawful activities taking place on unlawful foundations.

(4)

Fourth, the form and content of the ‘springboard’ relief should match the tensile strength of the ‘springboard’ unlawfully used by a defendant.

(5)

Fifth, in granting ‘springboard’ relief, the Court should take account of all the circumstances and grant relief which it thinks is fair, just and equitable.

Application of the Principles

9.

First, the form of the Order and ‘springboard’ relief should fit the facts. In this case, the Defendants were engaged in executing a concerted plan over many months effectively to acquire British Marine’s business by stealth without paying for it (Judgment [249] and [251]) which caused significant damage to British Marine (Judgment [149]) and in my view the case calls for the full protection of the Court (Judgment [283]). The Defendants thereby ‘stole a march’ on the Claimant and gained a significant unlawful advantage (Judgment [284]).

10.

Second, the ‘springboard’ relief should reflect and restrain the spectrum of the unlawful activities which made up the ‘springboard’. In this case, the Defendants obtained a substantial part of their unlawful ‘springboard’ advantage from the misuse of British Marine’s confidential information in furtherance of “Project Phoenix” (Judgment [167]). It is, therefore, appropriate that the injunctive relief should specifically cover the continued misuse of confidential information. Paragraphs 2, 4, 6 and 7 are part of the ‘springboard’ relief that I intend to grant and are not separate from it. The purpose of the relief identified in these paragraphs is not indirectly to enforce the employees’ confidentiality clauses themselves, but rather to assist in rectifying the unlawful consequences of their breach in the first place. For these reasons, I grant the relief in the form of paragraphs 2, 4, 6 and 7 but time limit it to the same period as the main ‘springboard’ relief in paragraphs 1, 3, 5 and 8, i.e. 28th April 2012.

11.

Third, in granting ‘springboard’ relief, the Court may restrain otherwise lawful activities taking place on unlawful foundations. The purpose of ‘springboard’ relief is to even up the playing field. It is no answer for the Defendants to say that they should not be restrained from continuing now with ‘permissible preparations’ for their new venture when they would not have reached this point of preparedness but for their months of previous unlawful activity. In any event, I do not accept that any of the steps listed in Mr Hearn’s Fifth Witness Statement amount to permissible ‘preparations’ (save perhaps for checking the Terms and Conditions and anodyne testing of the IT system).

12.

Fourth, the form and content of the ‘springboard’ relief should match the tensile strength of the ‘springboard’ unlawfully used by a defendant. As with the length of ‘springboard’ relief, so with content thereof: the equation regarding relative advantage gained is kinetic not merely linear (Judgment [284] and [285]).

13.

Fifth, when granting ‘springboard’ relief, the Court should take account of all the circumstances and grant relief which it thinks is fair, just and equitable. In this case it is relevant for the Court to have regard to the whole history of the Defendants’ unlawful conduct and propensities in the case (Judgment [43]-[168]) and their lack of candour in their evidence to the Court (Judgment [46], [110] and [144]). In such cases, the Order should take care to ensure that the Order leaves no ambiguity or ‘wriggle room’.

Further considerations

14.

For the avoidance of doubt, it is my intention to continue to restrain the Defendants from any further activities or preparations with regard to “Project Phoenix” until 28th April 2012, i.e. whether or not such activities or preparations might otherwise be regarded as ‘permissible’ or ‘impermissible’.

15.

For the sake of completeness, I should add that there is no difficulty with including the words “…or set up…”. In my view, their import is clear and an order including them would not fall foul of the ‘cardinal rule’ as to clarity enunciated by Balombe L.J. in Lawrence David Ltd. v. Ashton [1989] 1CR 123 at 132. Furthermore, in my view, the terms of Clause 8 of the employment contracts and written definition of ‘confidential information’ are sufficiently pellucid so as not to give rise to difficulties of the sort identified in Ocular Sciences Ltd v. Aspect Vision Care Ltd [1997] R.P.C. 289.

16.

It is noteworthy that this form of Order was not the subject of objection by the Defendants when first granted by the Court in October 2011. Nor does it appear to have caused any difficulty or lack of clarity in practice as to what the Defendants were or were not entitled to do under the injunction. The Order has achieved a stasis on the activities of the Defendants as regards “Project Phoenix” which is what it was intended to achieve. I intend that this should be continued until 28th April 2012.

17.

For these reasons, I grant final relief by way of ‘springboard’ relief in the form of the final Order attached to this Judgment, which is materially the same as that granted by me at the Interim Stage and that granted by Mr Nigel Wilkinson QC on 18th October 2011.

(2) Costs

18.

The Claimant seek costs on an indemnity basis and an interim payment.

19.

The Defendants submit: (i) The Claimant’s costs should be awarded on a standard basis not an indemnity basis. (ii) The Claimant should not be awarded costs up to the Order of Parker J. on 25th August 2011 because it was granted on the basis of non-competition covenants which have been found to have been invalid. (iii) The Claimant should be deprived of 30% of their costs after 25th August 2011 to reflect the significant increase in time and costs occasioned by the non-competition covenants issue which they lost.

(i) Indemnity costs

20.

The principles governing an award of indemnity costs under CPR 44.4 and 44.5 are well known and not in dispute. They are set out in cases such as Excelsior Commercial & Industrial Holdings Ltd v. Salisbury Hammer Aspden & Johnson [2002] EWCA Civ 87, Amoco UK Exploration v. BAO [2002] 1 BLR 135 and Three Rivers CD v. Bank of England [2006] EWHC 816 (Comm). They were considered recently by David Steel J. in Colour Quest v. Total Downstream [2010] 2 Costs LR 140 and Morgan J. in Digicel (St Lucia) Ltd v. Cable & Wireless [2010] 5 Costs LR.

21.

In my view, the present case involves conduct which does takes it “out of the norm” for five principal reasons:

(1)

The Defendants’ conduct is deserving of condemnation in that for many months they were knowingly engaged in unlawful conduct effectively aimed at acquiring British Marine’s business by stealth without paying for it (Judgment [109], [249] and [251]).

(2)

The Defendants allowed their commercial interests to take precedence over the rights and wrongs of the situation and were prepared to take the litigation risk (c.f. Langley J. in Amoco UK Exploration (supra) at paragraph [6]).

(3)

The Defendants assured the Claimant that they had complied with their obligations and intended to continue to do so; but the disclosure they were forced to make revealed a very different picture (Judgment [14]).

(4)

The Defendants have displayed a lack of candour with the Court at all stages (Judgment [46], [110] and [144] and see e.g. paragraphs 8, 18, 20 and 21 of Mr Dymoke’s first witness statement).

(5)

The Defendants persisted with their case notwithstanding that it was irreconcilable with their own contemporaneous documents (Judgment [44]) and only belatedly made some limited admissions in final submissions (Judgment [268]).

22.

For these reasons, in my judgment, this is a case in which it is appropriate to award costs against the Defendants on an indemnity basis under CPR 44.4.

(ii) Costs up to Order of Parker J.

23.

Mr Reade QC was right to characterise as ‘breathtaking’ the Defendants’ argument that the Claimant should not be awarded costs up to the Order of Parker J. on 25th August 2011 because the non-compete covenants were later found to have been invalid. I reject it. To accede to such an argument would be to allow the Defendants to profit from their own disingenuity and lack of candour at that stage. The reason why the Claimant’s claim for interim relief before Parker J. was based purely on breaches of the non-compete covenants (rather than ‘springboard’ relief itself) was because the Claimant was in the dark about the nature and scale of the Defendants unlawful activities. The true story only came to light when the Defendants were forced to give disclosure.

(iii) 30% discount.

24.

I also reject the Defendants’ contention that the Claimant’s costs should be discounted by 30% on an Elgindata basis to account for the time and cost of the non-compete covenant issue on which the Claimant did not succeed.

25.

The core issue in the trial was ‘springboard’ relief (as Mr Bloch said). This is what occupied the vast majority of the time, effort, documents, submissions and debate. The question of the validity of the non-compete covenants occupied relatively little time and, in any event, the process of analysis informed other parts of the case. The case of British Midland Tool v Midland International Tooling Ltd [2003] 2 BCLC 523 where Hart J. granted a 30% discount is distinguishable: it involved an issue which took up 50% of the trial.

26.

In the result, I grant the Claimant 100% of its costs to be assessed if not agreed. I also order the Defendants make an interim payment of £450,000 on account of the Claimant’s costs.

(3) Permission to Appeal

27.

The Defendants seek permission to appeal. The relevant principles are set out in CPR 52.3.

28.

Mr Bloch submitted that the Defendants should be granted permission to appeal on six grounds:

(1)

First, because arguably the Judgment should have considered the advantage gained from each breach individually before consideration of the cumulative effect (c.f. Judgment [252]).

(2)

Second, because ‘springboard’ relief is a difficult and developing area of the law and the ‘direction of travel’ is contrary to the Judgment (c.f. [180] and [181]), and anyway this area is ripe for further guidance by the Court of Appeal.

(3)

Third, because the Judgment was arguably wrong about the correct start date for any competitive advantage, i.e. that Mr Dymoke and Mr Hearn were entitled to have discussions between themselves about their futures.

(4)

Fourth, because the Judgment gave too little weight to the combined effect of low morale and the charisma of Mr Dymoke and Mr Hearn (‘the Pied Piper’ defence).

(5)

Fifth, because the Judgment failed to have regard to the irreparable harm the Defendants would suffer by reason of the grant of ‘springboard’ relief until 28th April 2012.

(6)

Sixth, because the findings as to damages were against the weight of the evidence.

29.

I am unpersuaded by any of these grounds. It is true that this case does involve some interesting areas of law (Judgment [169] ff.). And it may well be arguable that:

(1)

First, there is currently some lack of clarity as to the precise ‘direction of travel’ in the area of ‘springboard’ relief.

(2)

Second, there is a tension between (i) cases such as Kynixa v. Hynes [2008] EWHC 1495, British Midland Tool (supra) and the present Judgment on the one hand, which take a ‘restrictive’ approach, and (ii) cases such as Helmet Integrated Systems v Tunnard [2007] IRLR 126, Foster Bryant Surveying Ltd v. Bryant [2007] IRLR 425, Lonmar Global Risks Ltd v West [2011] IRLR 138 and Customer Systems Plc v. Ranson [2011] EWHC 3304, which take a more ‘liberal’ approach.

(3)

Third, there is need for further guidance from the Court of Appeal in the ‘springboard’ relief arena.

30.

In my view, however, the present case is probably not the right one to test these matters. I concluded that it was an overwhelming case on the facts and a clear case for ‘springboard’ relief, whatever the precise law (Judgment [248]). This was far from a marginal case on the ‘cusp’ of what was permissible. The Defendants’ activities mostly fell well on the wrong side of the (useful) table of ‘Permitted/ Prohibited’ activities on page 66 of Brearley and Bloch on Employee Covenants and Confidential Information (3rd Edition).

31.

For these reasons, permission to appeal is refused.

QBE Management Services (UK) Ltd v Dymoke & Ors

[2012] EWHC 116 (QB)

Download options

Download this judgment as a PDF (233.6 KB)

The original format of the judgment as handed down by the court, for printing and downloading.

Download this judgment as XML

The judgment in machine-readable LegalDocML format for developers, data scientists and researchers.