IN AN ARBITRATION CLAIM
AND IN THE MATTER OF APPLICATIONS UNDER S.67 AND S.68 OF THE
ARBITRATION ACT 1996
Royal Courts of Justice Strand, London, WC2A 2LL
Before :
SIR ROSS CRANSTON sitting as a Judge of the High Court
Between :
THE FEDERAL REPUBLIC OF NIGERIA Claimant - and - PROCESS & INDUSTRIAL DEVELOPMENTS Defendant
LIMITED
- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
MARK HOWARD QC, PHILIP RICHES QC and TOM PASCOE (instructed by
MISHCON DE REYA LLP) for the Claimant
IAN MILL QC and SIDDHARTH DHAR (instructed by KOBRE & KIM (UK) LLP) for the Defendant
Hearing dates: 13 and 14 JULY 2020
- - - - - - - - - - - - - - - - - - - - -
Approved Judgment
I direct that pursuant to CPR PD 39A para 6.1 no official shorthand note shall be taken of this Judgment and that copies of this version as handed down may be treated as authentic.
.............................
“Covid-19 Protocol: This judgment will be handed down by the judge remotely by circulation to the parties’ representatives by email and release to Bailii. The date and time for hand-down will be deemed to be 10:30 AM on 4 September 2020.”
SIR ROSS CRANSTON sitting as a Judge of the High Court:
Introduction
These are applications by the Federal Republic of Nigeria (“Nigeria”) for an extension of time to bring challenges under sections 67 and 68(2)(g) of the Arbitration Act 1996 (“the 1996 Act” or “the Act”). There is a related application for relief from sanctions to adduce new evidence in response to an enforcement application. The hearing before me was by order of Butcher J in The Federal Republic of Nigeria v Process & Industrial Developments Limited [2020] EWHC 129 (Comm). It occurred over two days but, as I explain shortly, there were later written submissions about what was said to be new evidence.
These challenges and the enforcement application concern arbitral awards by a London Tribunal relating to a gas processing contract (“the GSPA”) between Nigeria and Process & Industrial Developments Limited (“P&ID”) dated 11 January 2010. The Tribunal’s Final Award of 31 January 2017 ordered Nigeria to pay P&ID damages of US$6.6 billion, as well as pre- and post- judgment interest at 7 percent. The current outstanding amount is some US$10 billion.
Nigeria’s case for an extension of time is that the GSPA, the arbitration clause in the GSPA and the awards were procured as the result of a massive fraud perpetrated by P&ID, and that to deny them the opportunity to challenge the Final Award would involve the English court being used as an unwitting vehicle of the fraud. P&ID’s case is that the awards date back some three to five and a half years and it would be unprecedented to grant the extensions. Speed and finality are essential features of London arbitration and the case that there has been any fraud (which is denied) is at best weak.
The parties have produced a large volume of documents, some thirty-four bundles with hundreds of pages of evidence and thousands of pages of exhibits. It is not my function at this preliminary stage to decide whether a fraud took place. As Butcher J pointed out in ordering the hearing, it would tend to defeat the purposes of the 1996 Act for there to be a substantial investigation of the merits at this stage: at [30]. However, it has been necessary to consider a considerable amount of the material to decide firstly, whether, as Nigeria contended, there is a prima facie case of fraud and how strong that case is, and secondly, the steps Nigeria took to investigate the alleged fraud from late 2015. Both matters are relevant to the issues of whether Nigeria’s claim is barred altogether and whether time should be extended in its favour and relief from sanctions granted.
Following the hearing, P&ID submitted a Supplementary Note to comment on new evidence which it said had only now come to its attention, in particular a letter dated 5 June 2020 from Nigeria’s Attorney General and Minister of Justice, Mr Abubakar Malami SAN, to President Buhari. P&ID contended that the letter strongly supported the case it advanced at the hearing. On 21 August Nigeria sent a Note in response, together with the eighth witness statement in the proceedings from Mr Malami. The material is considered later in the judgment.
Background
P&ID and Project Alpha
The defendant, P&ID, was incorporated in the British Virgin Islands (“BVI”) on 30 May 2006 by Michael Quinn and Brendan Cahill, both Irish citizens. In July 2006 an associated company, Projects & Industrial Developments (Nigeria) Ltd (“P&ID Nigeria”), was established. P&ID had no assets, only a handful of employees, and was without a website or other presence.
Messrs Quinn and Cahill had a number of other companies relevant to this case, including an Irish company, Industrial Consultants International Ltd (“ICIL”). There was also Lurgi Consult Ltd (“Lurgi”), a Cypriot consulting company in the oil and gas industry. Its Nigerian counterpart had as its directors Adam Quinn, Mr Quinn’s son, and James Nolan. Other associated companies appear in the course of the judgment.
The narrative conveniently begins on 27 June 2006, when P&ID signed an engineering service agreement with General T. Y. Danjuma (retired), a prominent Nigerian businessman, for the undertaking of what was called Project Alpha. That was followed by a further engineering service agreement of 6 September 2006 with General Danjuma’s company, Tita-Kuru Petrochemicals Ltd (“Tita-Kuru”). Project Alpha concerned the design of a polypropylene plant in Badagry, south-west Nigeria.
In a letter to the Economic & Financial Crimes Commission (“EFCC”) dated 20 September 2019, Tita-Kuru states that one aspect of the arrangements with P&ID was that it would organise a gas offtake agreement from the Folawiyo gas field at Badagry, but that it later informed Tita-Kuru that it was unsuccessful in doing this. The letter continues that Mr Quinn of P&ID suggested that the engineering work undertaken could be used for a similar gas stripping plant at Calabar, capital of Cross River State in south-east Nigeria. The letter continues:
“3.1.6…We are therefore persuaded the studies, technology licencing fees and engineering designs that formed the basis of P&ID’s presentation to the Federal Ministry of Petroleum Resources were, in fact, ours…
3.2.2…[A]s per the matters in paragraph 3.1.6 hereof, we had paid the sum of $40m (Forty Million USD) to P&ID for the development of the Engineering work, Design and Off-take Consultancy Services which P&ID later used in their presentation to FMPR [Federal Ministry of Petroleum Resources] to secure the now disputed [GSPA].”
The letter also explains that there had been a falling out between Mr Quinn and General Danjuma but that later a memorandum of understanding was signed.
Steps leading to the GSPA
The reference in the Tita-Kuru letter to P&ID’s presentation to the Federal Ministry of Petroleum Resources (“MPR” or the “Ministry”) is to one of the steps in the negotiation of the GSPA. In October 2008 Mr Quinn made a power-point presentation at the Ministry. Slides 5 and 6 were computer aided design drawings, entitled “Propylene & Butane for Export, Phase 1” and “Propylene & Butane for Export,
Phase 2”. They were both marked in boxes in the right side, lower corner, “Project Alpha”.
Another step was that P&ID had written to Nigeria’s President Yar’Adua with a formal proposal on 7 August 2008. (Nigeria does not admit that this letter was sent.) Amongst other points the letter stated that:
“we are willing to fund, from our own resources, the entire US$700,000,000 for the gas processing facilities on land and we are also willing, if necessary, to participate in all or part of the financing of the gas gathering offshore portion of the project…”
On 18 December 2008 Dr Rilwanu Lukman was appointed as Nigeria's Minister of Petroleum Resources.
The following year there was correspondence and meetings between P&ID and members of the technical committee of the Ministry, among whose members were Dr M M Ibrahim (special senior technical assistant and head of policy at the government’s Oil & Gas Sector Reform Implementation Committee) and Mr Taofiq
Tijani.
In June 2009 Mr Quinn wrote to the office of the Minister of Petroleum Resources, for the attention of Dr Ibrahim, enclosing P&ID’s letter to the Ministry in mid-March “detailing our expenditure of more than 40 million US dollars to date on the project”.
There was a Memorandum of Understanding (“MOU”) signed on 22 July 2009 between the Ministry and P&ID Nigeria regarding the GSPA project.
On 1 December 2009 Dr Ibrahim sent a letter to P&ID indicating that Dr Lukman had “directed all stakeholders [to] fast track their processes”.
Just over a fortnight later, on 18 December 2009, Ms Grace Eyanena Taiga, legal director of the Ministry, sent a note to Dr Lukman advising him to sign the GSPA with P&ID. She wrote: “Subject to your comments to the contrary, I advise that HMPR [the Minister] signs these Draft Agreements to ensure a leap forward for Short Term Gas operations in the country as directed by Mr President.”
In his fourth statement for the court the Attorney General of Nigeria, Mr Malami, states that the GSPA did not obtain the requisite authorisation of the Bureau of Public Procurement or consent of either the Federal Executive Council or the Infrastructure Concession Regulatory Commission. Nor was it registered with the National Office for Technology Acquisition and Promotion. In his seventh statement, the Attorney General states that the individual at the Ministry responsible for compliance with these procedures was Ms Taiga.
The GSPA and immediate aftermath
The GSPA was entered into between Nigeria and P&ID on 11 January 2010. It was signed by Dr Lukman on behalf of Nigeria. His signature was witnessed by Ms Taiga. Mr Quinn signed the agreement for P&ID, and his signature was witnessed by Mr Alhaji Mohammed Kuchazi, an associate of Mr Quinn.
Under the contract Nigeria was to supply natural gas (“wet gas") at no cost to P&ID’s facility. For its part P&ID was to construct and operate the facility. It would process the gas to remove natural gas liquids – which P&ID was entitled to - and return lean gas to Nigeria at no cost, which would be suitable for use in power generation and other purposes. The contract was to run 20 years from Nigeria’s first regular supply of natural gas to the facility.
Clause 20 of the GSPA provided that, in the case of disputes, the parties could refer them to arbitration under the rules of the Nigerian Arbitration and Conciliation Act 2004. The venue of the arbitration was stated as London or otherwise as agreed by the parties. In his fourth statement the Attorney General, Mr Malami, states that the form of the arbitration agreement did not match the model reflected in a government circular in force at the time providing for arbitrations with their seat in Nigeria.
A month later, on 11 February 2010, the Government of Cross River State wrote to P&ID, confirming approval for a grant of land, subject to payment of NGN21,015,138 (about £44,500).
On 14 May 2010 Mr Quinn wrote as chairman of P&ID to the incoming group managing director of the Nigerian National Petroleum Corporation (“NNPC”), Nigeria’s state oil corporation. Mr Quinn requested assistance with the negotiations with Addax Petroleum, who were to provide the flared wet gas for the project. The letter stated that all necessary project finances were in place, 90 percent of the engineering designs were complete, a 50 hectare site had been allocated to P&ID by the Cross River State government, and Addax had confirmed its readiness to the Ministry to supply wet gas for the project.
Dr Lukman had ceased to be Minister for Petroleum Resources in March 2010. He was replaced the following month by Mrs Alison-Madueke. At the same time Mr Mohammed Bello Adoke SAN was appointed as the Nigerian Attorney General and Minister of Justice. As regards officials, Dr Ibrahim had left the Ministry on 1 February 2010. It seems that Ms Taiga left her position at the Ministry at some point later that year. Mr Tijani retired from the Ministry in January 2011. From 2011 until 2013 Ibrahim Dikko was legal adviser to the Ministry.
Between 2010 and 2012 P&ID wrote a number of letters to the Ministry, the NNPC and the President seeking implementation of the GSPA. There was a ministerial stakeholders meeting including P&ID in August 2010 and meetings with other stakeholders.
Commencement of arbitration
The GSPA was not implemented. On 22 August 2012 P&ID sent a Notice of Arbitration to Nigeria to commence proceedings under the Nigerian Arbitration and Conciliation Act 2004. Arbitration took place in three stages in London and resulted in three awards relating to jurisdiction, liability and quantum. Except to make sense of matters relevant to the current proceedings there is no need to set out the details of the arbitration and associated proceedings, which are dealt with in Butcher J’s judgment in Process & Industrial Developments Limited v The Federal Republic of Nigeria [2019] EWHC 2241 (Comm); [2019] 2 Lloyd's Rep 361, [7]-[34].
In broad outline, P&ID and Nigeria appointed arbitrators in September and November 2012 respectively. In its initial statement of case P&ID alleged that Nigeria did not deliver the wet gas as required under the GSPA and had repudiated the contract, a repudiation which it had accepted. It claimed some US$6 billion in lost profits. P&ID served its Statement of Case in late June 2013. Nigeria’s notice of preliminary objection in October 2013 disputed the tribunal's jurisdiction on the grounds that: (1) the GSPA was void because the Ministry, as a government body, did not have legal capacity to enter into contracts; and (2) the contract breached section 54 of the Companies And Allied Matters Act 2004, which requires foreign companies to carry out any business through a local subsidiary.
Mr Olasupo Shasore SAN was appointed as counsel for Nigeria in the arbitration. Mr Shasore was a former Attorney General of Lagos State, author of a textbook on Nigerian arbitration and a past President of the Lagos Court of Arbitration. He worked at a law firm, Ajumogobia & Okeke. The senior partner of that firm has given evidence to the EFCC that Mr Shasore kept his involvement in the case hidden and ran it through a different firm, Twenty Marina Solicitors, which was used to provide secretarial services. In a statement to the EFCC dated 24 December 2019, Mr Shasore has said that he was paid a fee of US$2 million for the first two stages of the arbitration, including disbursements.
On 14 February 2014 P&ID served its submissions on preliminary issues, with a witness statement from Mr Quinn and an expert report from Justice Alfa Belgore.
Evidence of Mr Quinn
Mr Quinn’s 34-page witness statement was dated 10 February 2014, which he gave as chairman of the company. Mr Quinn died in February 2015, before the liability hearing, and never gave evidence in person. In the arbitration P&ID relied on the factual evidence contained in the statement.
After some introductory paragraphs, Mr Quinn stated at paragraph [4] of his statement that the GSPA represented a substantial project involving anticipated profits of $5 to $6 billion for P&ID over a 20 year period. The paragraph continued: “It was the culmination of years of research by my team of engineers into the production of clean energy from natural gas.”
Mr Quinn then set out what he said was his experience in Nigerian infrastructure projects (paragraphs [10]-[16]), before turning to the incorporation in July 2006 of P&ID Nigeria - the operating company – and P&ID, the BVI-incorporated company which signed the GSPA. As to P&ID he said: “I believe that the Government regarded the involvement of a BVI entity as a contracting party, rather than the Nigerian entity, to be commercially beneficial, especially from the perspective of the sale of NGLs [natural gas liquids] on the international markets”: para [21].
After passages on natural gas and power generation, the power crisis in Nigeria, and the country’s gas master plan, Mr Quinn’s statement turned to the nature of the project, the construction of a gas stripping plant. Work started in earnest, Mr Quinn said, in 2006: para [41]. A little later he said:
“47. During the course of the next two years, we made good progress and reached a very advanced stage of the preparatory engineering work necessary to implement such a project on the ground. I would estimate that the total costs sunk into the preparatory work during that period were in excess of US$40 million, including initial feasibility studies, the cost of licences for the technology required to operate the gas stripping plant and the polypropylene plant respectively, the production of detailed engineering drawings and our own internal project management costs.”
48. By way of example, extensive work was commissioned from various specialist engineering companies…The cost of the work from these 3 companies alone was about $29 million…
49. By the end of the first 2 years of our work on the Project, we had put together a completed engineering package … which comprised about 100 volumes of documentation, together with a 3-D model of the plant…”
Mr Quinn then summarised what he said were the discussions with the government leading to the signing of the GSPA. Under the heading “Implementation of the GSPA”, Mr Quinn referred to a number of steps which he said P&ID had taken. One was that a site for the onshore gas stripping plant “had been selected by P&ID and secured…[and] on 16 February 2010 approval was granted, by the Government of the
Cross River State, to P&ID, of the allocation of Parcels 1 & 2 of Energy City (Industrial) at Adiabo…”: para [109]. Mr Quinn added:
“110. On 14 May 2010, I wrote to NNPC [Nigerian National Petroleum Corporation] on the progress made by P&ID. I pointed out that all of the project finance was in place, 90 percent of the engineering designs had been completed, a 50 hectare site had been allocated to P&ID by the Cross River State Government…”
Mr Quinn’s statement then contained an account of what he said was the Nigerian government’s repudiation of the GSPA.
To his statement Mr Quinn exhibited the power-point presentation given at the Ministry in October 2008.
Jurisdiction Award and attempts at settlement
In its Partial Final Award of 3 July 2014, the Tribunal determined that it had jurisdiction and that the GSPA was valid and binding between the parties (the
“Jurisdiction Award”). The Tribunal noted that in May 2014, Twenty Marina Solicitors had emailed the Tribunal stating that it would not be able to lodge Nigeria’s skeleton argument by the deadline or attend the jurisdiction hearing due to a difficulty in obtaining instructions. There was no request for an adjournment of the hearing, and the Tribunal dispensed with an oral hearing for the purposes of the award.
P&ID served its statement of case on liability on 28 June 2014. On 21 July 2014 the Tribunal ordered that Nigeria serve its statement of defence by 19 September 2014 (Procedural Order No.5). Nigeria did not comply.
There were then attempts at a settlement. On 17 July 2014 Mr Shasore had written to Nigeria’s Attorney General, Mr Adoke, that “there appears to be a lack of exonerating facts or any documentary evidence with which to defend the claim” and urged a “possible settlement”. On 11 August 2014 Mr Adoke then wrote to President Goodluck Jonathan expressing his agreement with Mr Shasore’s advice of mid-July that there were no “exonerating facts” and therefore “no legal grounds to defend the claim”.
Separately the NNPC wrote to the Minister for Petroleum Resources, Mrs AlisonMadueke, on 1 September 2014, agreeing with the Attorney General and outside counsel that the Ministry had “a bad case”. To that end it recommended that settlement be explored but that Nigeria should, nonetheless, file a defence. On 11 November 2014 the Attorney General wrote to Mrs Alison-Madueke, including the advice from Mr Shasore, urging her to pursue settlement discussions.
On 11 November 2014 Ms Folakemi Adelore, legal adviser to the Ministry from 2013 to 2017, sent a memorandum to the permanent secretary of the Ministry recommending a settlement with P&ID.
On 18 November 2014, US$100,000 of cash was deposited into Ms Adelore’s account in ten US$10,000 tranches. As explained later in the judgment, Mr Shasore and Ms Adelore accept that Mr Shasore was the source of the payment. There was an equivalent payment of US$100,000 to Mr Ikechukwu Oguine, who was the coordinator, legal services at the NNPC. Both Mr Shasore and Mr Oguine accept that Mr Shasore made the payment.
In December 2014 Mr Shasore, Ms Adelore and Mr Oguine travelled to London for settlement negotiations with P&ID.
On 30 December 2014 Ms Adelore wrote a memorandum to the Ministry’s permanent secretary. She stated that there was no doubt the Ministry was in breach of the GSPA; the negotiating team was apprehensive that the Tribunal might award P&ID’s claim of US$5.9 billion; and Nigeria should offer a lower amount which P&ID might accept.
The Liability Award
The Tribunal made Procedural Order No.6 on 16 February 2015, noting that Nigeria had missed an agreed, extended deadline of 3 October 2014 for filing its defence for the liability hearing, and ordering it to do so by 27 February. Nigeria’s statement of defence was filed and served by Mr Shasore on 27 February 2015.
On 17 March 2015 Mr Adoke, the Attorney General, forwarded a letter from Mr Shasore to the Minister for Petroleum Resources, Mrs Alison-Madueke, stating that “notwithstanding our line of defence, the Federal Government is still liable for failure to supply the requisite gas”. On 16 April 2015 Mr Shasore wrote to Mr Adoke, stating that the Ministry’s defence was in “grave need of evidence, documents and witnesses”, and asking for an “urgent response” on a proposal to settle the claim.
In response to Procedural Order No.8 directing Nigeria to serve its evidence and supporting documents by 1 May 2015, Nigeria served the witness statement of Mr Oguine, legal coordinator at the NNPC. The statement explained why Nigeria was
unable to supply gas to P&ID and argued that its only role was as a “facilitator” between P&ID and the oil companies. There were no exhibits to the statement.
The Tribunal held a case management hearing by telephone on 6 May 2015. Neither side applied for cross-examination of witnesses. Following the case management hearing, the Tribunal made Procedural Order No.9 by consent. It required Nigeria to serve, within 48 hours, “a statement of any primary facts alleged in the evidence of Mr Michael Quinn which are challenged and of any other facts alleged to be relevant to the question of liability”. The Tribunal set down a hearing for 1 June, with 2 June in reserve.
On 12 May 2015 Mr Shasore served Nigeria’s statement of disputed facts. In substance they occupied less than a page and were six in number: P&ID’s knowledge that the Nigerian government had commenced building a pipeline; whether P&ID initially regarded Lagos as an attractive area for the project; whether the purpose of the GSPA was for P&ID to take wet gas free of charge from Nigeria; whether the government had access to “unlimited” supplies of natural gas in the Calabar area; whether Phase 1 of the contract was planned to take two years to implement after the grant of government approvals; and whether Nigeria was obliged to deliver wet gas free of charge to the site of the plant.
P&ID served its written arguments for the hearing on liability on 25 May 2015. On 28 May 2015 Nigeria did likewise, contending inter alia that the Ministry lacked capacity to enter the GSPA, that P&ID failed to fulfil its obligations under the GSPA, that construction of the gas processing facilities at Calabar was a precondition to Nigeria supplying wet gas, that the GSPA was for the supply of ascertained wet gas, misrepresentation by P&ID, fundamental change in circumstances, illegality, and that the GSPA was contrary to public policy and international law.
The liability hearing began at 10am on 1 June 2015 and ended early in the afternoon the same day. In the course of submissions on the first issue of the Ministry’s capacity to enter the GSPA, Mr Shasore stated that he hoped to cross-examine Mr Quinn on the matter. The chairman responded that there had been no application to crossexamine Mr Quinn. He added that P&ID had stated that it did not need to rely on the disputed facts Nigeria had raised on 12 May 2015, so that there was no scope for cross-examination.
Mr Shasore replied that that was not his understanding, and he applied to crossexamine Mr Quinn, at which point P&ID’s advocate informed the Tribunal that Mr Quinn had died earlier in the year. The Tribunal made a formal ruling: there was no application to cross-examine Mr Quinn, and under Procedural Order No. 9 Nigeria had to serve a statement of any primary facts in Mr Quinn’s affidavit which it challenged, and any other facts alleged to be relevant. Nigeria had done this, but P&ID took the view that none of the challenged facts were relevant to its claim and were content that those facts should not be accepted. The hearing continued.
In reply submissions following the hearing, Mr Shasore returned to his inability to cross-examine and asserted that his statement of disputed facts essentially challenged all the facts in Mr Quinn’s statement.
The Tribunal issued its Partial Final Award concerning liability on 17 July 2015, finding that Nigeria had repudiated the GSPA and that P&ID was entitled to damages (“the Liability Award”). As to the evidence, the Tribunal said at paragraph [35] that “although Mr Ikechukwu Oguine made what was called a witness statement, he gave no relevant evidence”; his statement consisted of references to documents on the record and submissions in similar terms to those made by Mr Shasore. The Tribunal used Mr Quinn’s evidence, where it had not been contested by Nigeria, as the factual basis of events preceding and subsequent to the GSPA. The Tribunal dismissed Mr Shasore’s defences to the claim.
President Buhari elected and the Quantum/Final Award
Having won the elections, President Muhammadu Buhari was sworn in on 29 May 2015. Professor Yemi Osinbajo became the vice-president. On 11 November 2015, Mr Malami was appointed as Attorney General and Minister of Justice. He continues in that role to the present day. In his sixth statement for this court he recalls that after his appointment he studied the arbitration case file and noticed some lapses in how the matter had been handled.
Meanwhile, on 27 October 2015, the Tribunal had made Procedural Order No.10, noting that Mr Shasore had informed the Tribunal that he was without instructions. The order required P&ID to serve its evidence on quantum and for Nigeria to serve reply evidence.
On 23 December 2015 Nigeria applied to this court for orders to make an out of time application to set aside the Liability Award on grounds of internal inconsistency in the Tribunal’s reasoning, the Tribunal’s failure to deal properly with the authority argument, and the Tribunal’s failure to give reasons that Nigeria’s breach was repudiatory. On 10 February 2016 Phillips J considered the application on the papers (as is customary) and rejected it: the application was more than four months after the expiry of the 28 day time limit, and for reasons he explained Nigeria had not shown compelling reasons for an extension. In refusing to extend time, Phillips J also took into account that the grounds had no merit, for reasons he explained.
Nigeria then filed an originating motion in the Nigerian Federal High Court. Dated 24 February 2016, it sought an order: (i) extending time to set aside the Liability Award; and (ii) setting aside and/or remitting for further consideration all or part of the Liability Award. On 5 April 2016 Nigeria also sought an order restraining the parties from participating in the arbitration, pending the court’s determination of the 24 February 2016 application. That was granted on 20 April 2016.
In response to the position where Nigeria had made an application to the Nigerian court, the Tribunal made Procedural Order No. 12 on 26 April 2016, setting out its reasons for finding that the seat of the arbitration was England, not Nigeria. Nigeria challenged the Order in the Federal High Court on 9 May 2016, but that application was struck out for want of prosecution later in the year.
On 24 May 2016 the Nigerian court made an order: (i) extending time for Nigeria to apply to set aside the Liability Award; and (ii) setting aside and/or remitting for consideration all or part of the Liability Award.
The Tribunal held a two-day hearing on quantum in late August 2016. Nigeria participated, while maintaining its position as regards the Liability Award.
By this time Mr Shasore had been replaced as Nigeria’s counsel by Chief Bolaji Ayorinde SAN. In a letter to the Vice President on 29 March 2017 the Attorney General, Mr Malami, stated that Mr Shasore had failed to cooperate properly in handing over material when his (the Attorney’s) office assumed the conduct of the case from the Ministry in mid-2016.
For the purposes of the quantum hearing both sides commissioned expert reports. P&ID had an expert report prepared by Berkeley Research Group LLC (“BRG”), dated 19 August 2016. Amongst other things it concluded, from reviewing P&ID’s CAD (computer aided design) model and its proposal to the government, that it was well advanced in its preparation to build the facility.
The Tribunal issued its final award on quantum on 31 January 2017 (the “Final
Award”). In part E, “Findings on liability”, beginning at paragraph [29] it recalled its findings in the Liability Award. The evidence of P&ID, it said, consisted of a statement of Mr Quinn, parts of which it quoted, including his paragraph [110], set out earlier in the judgment. It then recalled Procedural Order No. 9, and that Nigeria had served a statement of the facts it challenged, but which P&ID had elected not to rely on.
Then in part G, “Measure of Damages” the Tribunal stated at paragraph [50] that the evidence showed a high degree of likelihood that if the government had been willing to perform, “P&ID was fully prepared to acquire the land and start constructing the plant”, quoting again from Mr Quinn’s statement. At paragraph [51] the Tribunal recalled Procedural Order No. 9, that Nigeria had not disputed any of the matters the Tribunal had mentioned and concluded: “P&ID thus showed every sign of being willing, indeed anxious, to implement the project and there is no dispute over its ability to have done so.”
By a majority the Tribunal found that, had Nigeria not repudiated its obligations under the GSPA, P&ID would have performed its obligations and had suffered loss. That was measured by the income it would have achieved in the 20 years of the contract from the sale of the NGLs which would have been extracted from the wet gas, less capital expenditure (“capex”) of some $500 million and $50m operating expense (“opex”) per annum. It awarded P&ID lost profits of US$ 6.6 billion, together with pre- and post-award interest of 7 percent.
Response to the Final Award
On 2 March 2017 there was a meeting at the Attorney General’s office to consider all options available to Nigeria. The meeting included Mr Malami, the Attorney General, the Nigerian law firm representing Nigeria in the arbitration and representatives of the Ministry and the NNPC.
Following that meeting, on 13 March 2017 Mr Malami wrote to Vice President Osinbajo, who was acting president at the time, exploring five “scenarios” and making recommendations on each. The first was to negotiate a reasonable settlement. The second was to undertake a “forensic and extensive examination of the original contract, Award and other Processes to discover loopholes to upset or vary the Award.” The merits were said to be that a loophole might be discovered, for example fraud, technical grounds or a conflict of interest of the arbitrators. The other options were to inquire whether there was the possibility of an appeal, an investigation by the EFCC and a challenge to the recognition and enforcement of the award.
Mr Malami wrote further to the Vice President on 17 March 2017, following a meeting on 13 March where the scenarios in the 13 March letter were “extensively deliberated”. Scenario 1 was now expressed as “the urgent need” (emphasis in original) to negotiate a settlement. The scenario about involving the EFCC was that it should be directed to undertake a discreet investigation of the matter, and also to ascertain the personalities and beneficiaries behind P&ID.
There was a further letter from Mr Malami to the Vice President dated 29 March 2017. On 6 April 2017 the Vice President approved in manuscript on the letter its proposal to pursue settlement negotiations.
There followed on 16 May 2017 (and afterwards) without prejudice settlement discussions with P&ID. After P&ID stated in September 2017 that it intended to enforce the Final Award, on 7 December 2017 the Vice President granted approval to negotiate further. However, settlement negotiations broke down.
The Attorney General, Mr Malami, together with the Minister of State for Petroleum Resources wrote to the Vice President on 23 May 2018 in light of US enforcement proceedings which P&ID had initiated, recommending the reopening of negotiations with P&ID while efforts were being made as regards the enforcement proceedings.
On 12 June 2018 the Vice President’s office reported that he had agreed with the recommendation and would take up the matter with the President. That same day, 12 June 2018, the Vice President wrote to the President recommending the reopening of negotiations with P&ID. The President approved this recommendation on 26 June 2018.
There was a meeting on 12 July 2018 in anticipation of settlement negotiations involving Nigeria’s international legal representatives, Curtis, Mallet-Prevost, Colt & Mosle LLP (“Curtis”), the Attorney General, Mr Malami, and Nigerian officials. A memorandum of the meeting records that Nigeria still preferred a reasonable settlement with P&ID. It added that the Nigerian team also alleged that there may be fraud involved in the circumstances surrounding the GSPA. However, the Curtis team
“pointed out that in order to advance fraud…there is need to have concrete evidence of same”.
Negotiations with P&ID the following day, 13 July 2018, were unsuccessful.
Enforcement of the Final Award
Meanwhile, on 16 March 2018 P&ID applied to this court under section 66 of the 1996 Act for an order that it have leave to enforce the Final Award of 31 January 2017. Nigeria did not file an acknowledgement of service in time and applied for relief from sanctions. On 21 December 2018 Bryan J granted relief from sanctions: Process & Industrial Developments Limited v The Federal Republic of Nigeria [2018]
EWHC 3714 (Comm). Meanwhile, on 28 March 2018, P&ID had commenced enforcement proceedings in the United States District and Bankruptcy court for the District of Columbia.
Nigeria raised a number of objections to the section 66 application, including that
London was not the seat of the arbitration. In his judgment in Process & Industrial Developments Limited v The Federal Republic of Nigeria [2019] EWHC 2241 (Comm); [2019] 2 Lloyd's Rep 361, handed down on 16 August 2019, Butcher J held that the Tribunal had correctly construed the arbitration clause in the GSPA that London was the seat of the arbitration, and its decision created an issue estoppel precluding Nigeria from raising the issue at the enforcement stage. He then went on to dispose of various grounds Nigeria had raised against enforcement, including that it would be against public policy. The application by P&ID to enforce the Final Award as a judgment or order of the court was consequently granted.
At a hearing on 26 September 2019 to consider consequential matters, Butcher J gave Nigeria permission to appeal: Process & Industrial Developments Limited v The Federal Republic of Nigeria [2019] EWHC 2541. In the course of his judgment he said:
“[15]…[T]here has been some mention before me of there being an investigation conducted by Nigeria into the award of the GSPA and related matters. There is a suggestion that there may have been some sort of fraud, conspiracy or tax evasion. Those were not grounds which were relied upon before me at the hearing in June as reasons why the Final Award should not be enforced. They are not relied upon now as reasons for the grant of permission to appeal nor as grounds of appeal. On the contrary, Mr Matovu's skeleton argument states in terms that ‘The court is not asked to act on these investigations or convictions at the present hearing.’ Those allegations have accordingly played no part in my decision in relation to permission to appeal.”
Nigeria launched the current challenges under sections 67 and 68(2)(g) of the 1996 Act on 5 December 2019. As we have seen, on 24 January 2020 Butcher J ordered Nigeria’s applications for an extension of time and relief from sanctions to be heard as preliminary issues and not as part of a rolled up hearing with the substantive applications: The Federal Republic of Nigeria v Process & Industrial Developments Limited [2020] EWHC 129 (Comm). That is the present hearing.
On 29 January 2020 Flaux LJ, the supervising Lord Justice of the Commercial Court, stayed the appeal from Butcher J’s enforcement order pending the outcome of this hearing.
EFCC investigations
The EFCC is a statutory body under the Economic and Financial Crimes Commission (Establishment) Act 2004, with power to conduct investigations into whether any person has committed an offence under the legislation constituting it or any other law relating to economic and financial matters.
2016 investigation
In February 2016 the Attorney General, Mr Malami, asked the EFCC to investigate P&ID.
This investigation was the result of a letter of 1 February 2016 from Stephenson Harwood to Ms Adelore, the legal advisor to the Ministry. Nigeria had engaged the firm to assist it. It had written recommending that sufficient resources be deployed to challenge the legal and expert evidence submitted by P&ID. Further, it said, a credible investigations company should be appointed to carry out investigations into the history, financial capability and track record of P&ID given its offshore structure, apparently small size and lack of significant track record. The letter commented that this may assist Nigeria at the quantum stage of the arbitration either directly or indirectly.
For the purposes of its inquiry, the EFCC requested that the legal directors of the Ministry (Ms Adelore) and the NNPC (Mr Oguine’s successor) be released for interviews as part of the investigation into what it described as a case of conspiracy, abuse of office and misuse of public funds. From late February 2016 until 2 March 2016 these officials were interviewed and provided the EFCC with documents relating to the GSPA and the arbitration. In a briefing note for the EFCC, Ms Adelore criticised Mr Shasore’s strategy in the arbitration. In April-May 2016 the EFCC conducted further meetings with the NNPC and reviewed the GSPA, the July 2009 MOU and other documents received from both the Ministry and the NNPC.
On 16 June 2016 the EFCC submitted an interim report. In the section headed “Findings”, the report canvassed the background to the GSPA. It noted that the process of awarding the GSPA
“was significantly hinged on the report of the technical committee of the [Ministry] [and] had the certification and recommendation of the legal unit of the Ministry and that the agreement was signed by the Legal Adviser, Grace Taiga, as a witness to the MOU and the [GSPA]”.
The report observed that the Tribunal appeared to have acted on the material before it, although there were “strands of information that the panel acted out of the scope of its work. Focus should be the underlying transaction, if anything.”
The interim report then set out short conclusions and recommendations. P&ID, it said, was not entirely blameless “as there are key gaps noticed in the transaction for which it may be necessary to go beyond their capacity.” It added: “It is definite that the award of the contract by the [MPR] was a function of the recommendation of the technical committee of the Ministry.” While the technical committee of the Ministry had experts, the report continued, “the findings of gaps in the reasons for default by parties might require a further investigation”. It recommended a
“further detailed investigation of the circumstances surrounding the award of the contract and the key parties to the transaction”.
EFCC investigation beginning June 2018
On 13 April 2018, the NNPC wrote to the Attorney General, Mr Malami, reminding him that at a meeting on 2 March 2017 it had identified deficiencies in the GSPA and suggesting among the options for resolving the P&ID matter that there be an independent forensic examination of the entire case file.
As referred to earlier, the Attorney General together and the Minister of State for Petroleum Resources had written to the Vice President on 23 May 2018 recommending further negotiations with P&ID. The Vice President had agreed, adding in manuscript on the letter that he was still of the opinion that the underlying transaction was “a fraud on the nation”, and that perhaps there might be “a need to independently review this view and investigate the entire affair more diligently”.
On 12 June 2018 the Vice President’s office (no doubt using his manuscript on the joint ministerial letter) replied formally to the Attorney General and Minister of State, stating his view that “the whole arrangement amounts to a fraud on the nation”, and that he had therefore additionally recommended to the President “the need to independently investigate all the relevant circumstances”.
That same day, 12 June 2018, the Vice President wrote to the President recommending that as well as reopening negotiations with P&ID he might also wish to direct the acting chairman of the EFCC “to independently investigate all relevant circumstances surrounding the transaction underlying the arbitral award with a view to determining whether or not there was a fraudulent intent in the conception of the agreement”.
The President issued a direction on 26 June 2018 that the Ministry and the Ministry of Justice was to provide all necessary information, documents and support to the EFCC to enable a thorough investigation of the circumstances surrounding the GSPA and subsequent events. In addition, he directed the Director-General of the National Intelligence Agency to investigate P&ID with a view to uncovering the identities of all the promoters, directors and shareholders of the firm. The President also ordered an urgent review into any lapses that had led to the current situation.
On 28 June 2018 the Attorney General, Mr Malami, wrote to the acting chairman of the EFCC, passing on the President’s instructions to conduct “a thorough investigation of the circumstances surrounding the [GSPA] and the subsequent events”. As well he sent the documents his department had as part of the inquiry.
In his sixth witness statement in these proceedings, Mr Malami states that the EFCC investigation began with research into open and closed sources, including the profiling of some thirty potentially relevant suspects. In August 2018 information requests were sent to various government agencies. In January 2019 the EFCC requested further information from the Ministry of Lands at Cross River State and the Federal Inland Revenue Service.
Events after Butcher J’s judgment of 16 August 2019 including P&ID’s conviction
Following Butcher J’s judgment of 16 August 2019, which meant that P&ID could enforce the Final Award, on 20 August 2019 Nigeria’s Solicitor General involved the Nigerian police in the investigation into P&ID. The Attorney General states in his sixth witness statement that this was because of the EFCC’s limited remit to financial and related matters.
On 28 August 2019 the Federal Inland Revenue Service informed the EFCC that P&ID had not opened a tax file. Early the following month, on 3 September 2019, the Special Control Unit against Money Laundering reported that P&ID Nigeria had failed to register its activities with it.
In a letter of 4 September 2019 to the EFCC, the Director of Lands of Cross River State wrote that a letter of allocation was only issued to applicants on payment of all the land charges and fees within the 120 days specified. P&ID could not claim that the land had been allocated to it in 2010, since there was no proof of payment and no issuance of a Certificate of Occupancy.
Criminal proceedings against P&ID, Ms Taiga, Mr Cahill and Mr Kuchazi were commenced on 17 September 2019. Two days later, on 19 September 2019, P&ID and P&ID Nigeria pleaded guilty before Ekwo J in the Federal High Court to ten and eleven counts respectively relating to conspiracy to defraud Nigeria, money laundering, tax evasion and trading without proper authorisations. The convictions were on evidence given by an officer of the EFCC.
EFCC: interview and statements
The EFCC began interviews in September 2019. Included among those interviewed was Ms Taiga, who had been the senior lawyer in the Ministry until 2011. She was detained between 3 September 2019 and 21 September 2019. She gave a statement on 11 September 2019. She has complained about her treatment when detained.
The EFCC interviewed Mr Tijani under caution on 4 September 2019. At the time of the GSPA he was a member of the Ministry’s technical committee. He told the EFCC that the committee’s role was to conduct due diligence on projects, including P&ID’s. He denied wrongdoing, receiving gifts and recalled that he had no objections to P&ID’s project and subsequently recommended it.
During a further interview on 15 November 2019 – once EFCC had accessed certain bank records – Mr Tijani accepted that he had received bribes from P&ID in return for overlooking shortcomings in its bid. His account is also contained in a witness statement for this court; it is summarised later in the judgment. In response to a letter from Mr Tijani in early December 2019, the Attorney-General entered a nonprosecution agreement with him on 8 January 2020.
In a statement to the EFCC on 13 September 2019 Mr Oguine, legal director at the NNPC at the time, said that Mr Shasore – counsel for Nigeria in the arbitration - offered him US$100,000 towards his (Mr Oguine’s) expenses. Mr Oguine initially declined but eventually took the money on the basis that it would be repaid as a loan. No part had yet been repaid. Mr Oguine also stated that he was charged with obtaining potential witnesses of fact for the liability hearing before the Tribunal. No witnesses could be found, so Mr Shasore prepared a witness statement which he reviewed and signed.
As explained earlier in the judgment, in a letter to the EFCC on 20 September 2019 General Danjuma’s company, Tita-Kuru, stated, in effect, that P&ID had stolen its plans for a gas stripping plant which it then used to obtain the GSPA.
Mr Shasore, who conducted the arbitration for Nigeria at the jurisdiction and liability stages, was interviewed on 24 December 2019. He told the EFCC that he made personal gifts of US$100,000 each to Ms Adelore (the senior lawyer at the Ministry) and Mr Oguine (legal director at the NNPC).
In an interview on 6 and 7 May 2020 Ms Adelore accepted that she received an unsolicited payment of US$100,000 in cash from Mr Shasore, which she had a colleague collect from Mr Shasore’s office. She has told the EFCC that she felt Mr Shasore was working against Nigeria’s interests in the arbitration.
EFCC: bank records
During its inquiries EFCC obtained bank statements and Swift records of interbank payments in relation to various accounts. Among the information obtained from September 2019, and the date EFCC obtained it, is the following (described in greater detail later in the judgment under “Payments/bribes”).
Ms Taiga received two cash transactions of US$10,400 and US$6,500 into her Access Bank account (but not linked to P&ID) (information EFCC obtained on 27 September 2019). There were payments in 2017 into her Zenith Bank account from Eastwise and ICIL (information EFCC obtained on 2 October 2019). Her daughter received payments from ICIL, Ireland, in March 2019 (information EFCC obtained from Citibank NA, London, 2 March 2020).
Dr Lukman opened a US Dollar account at GT Bank on 16 January 2009, with an initial cash deposit of US$10,000. Dr Lukman then deposited a further US$10,000 of cash into another GT Bank account on 8 April 2009 (information EFCC obtained on 5 October 2019).
Mr Tijani received two payments from Lurgi totalling around £30,000 in April 2014 and April 2015 (information EFCC obtained early November 2019).
Dr Ibrahim, a member of the technical committee reviewing the GSPA, opened a US dollar account on 28 April 2008 under the name of his company, Equatorial Petroleum Coastal & Process Limited, with an initial cash deposit of US$10,000. There were further periodic cash deposits totalling US$69,300 until 2015. On 28 October and 1 December 2008 there were also two cash deposits totalling NGN 4,000,000 (approximately £8,500) into his personal account at Firstbank.
In March this year Nigeria applied to the US District Court for the Southern District of New York under 28 USC [United States Code] § 1782(a) to obtain discovery of bank accounts at ten different banks. P&ID intervened in the course of the application. It stated that it did not object to the order although its submission to Judge Schofield was that the use of the information obtained should be limited to criminal prosecutions in Nigeria.
The US court made disclosure orders on 7 May 2020. As a result of the application
Nigeria obtained information, including payments to Ms Taiga’s daughter in 2009 and 2012.
Role of acting chairman of EFCC, Mr Ibrahim Magu
After the hearing I received written submissions relating to the role of acting chairman of EFCC, Mr Ibrahim Magu. On 5 June 2020 the Attorney General, Mr Malami, had sent a letter to President Buhari headed “Flagrant abuse of public office and other infractions committed by Mr Ibrahim Magu, acting chairman of the Economic and Financial Crimes Commission”. In the course of the letter the Attorney General stated that as regards the investigation of P&ID, although he had passed on the President’s direction in June 2018, the EFCC “did not accord this presidential directive with any serious attention until a year after around July/August when the scale had already tilted dangerously against Nigeria”. In view of the delay, the Attorney General continued, he had involved the police. That had prompted Mr Magu to prosecute charges against P&ID, but without recourse to the wider team.
Mr Magu was detained on 6 July 2020 and a panel is investigating matters. On 31 July 2020, after the hearing before me, a Nigerian news outlet, The Cable, published what purported to be a copy of the Attorney General’s letter of 5 June 2020 and the reply of Mr Magu. In Mr Magu’s reply he says that the EFCC investigation was conducted expeditiously in 2018-2019, and that a staggering and unprecedented volume of work was done in less than a year.
After The Cable report, on 4 August 2020, the Attorney General wrote again to the President under the same heading. He sought to clarify that his complaint was against
Mr Magu and his lack of support within the EFCC for the P&ID investigation. The EFCC had begun the investigation, he said, but it had taken a lot of coercion from his office to have the investigation progress. Under Mr Magu, said the letter, the EFCC did not share information with the Attorney General’s office or the police.
In a further statement for the court Mr Malami states that he has never seen what is reported as Mr Magu’s letter and his understanding is that the President has never received it. He states that despite his criticisms of Mr Magu’s personal handling of the EFCC investigations into P&ID, the investigation itself made excellent progress.
Payments/alleged bribes
In his fourth witness statement in these proceedings the Attorney General, Mr Malami, acknowledges that fraud has been endemic in Nigeria, until the arrival of President Buhari in 2015 at the very highest levels, and especially in the oil and gas sector. He adds that the endemic corruption, which the present regime was taking great strides to eliminate, was in existence at the time the GSPA was entered into, when the dispute arose and during the early stages of the arbitration.
The alleged bribes which Nigeria relied on for the purposes of the hearing were collected in a schedule. In summary the date and amount of these payments, their source, and the date Nigeria uncovered them, are as follows:
Ms Taiga, senior legal adviser to the Ministry at time of GSPA
On 19 and 20 August 2010 Ms Taiga made two payments into her Access Bank account, in total US$10,400. Ms Taiga says this cash may well have come from the sale of a car or property from her late mother’s estate. In her second statement, she says that it represented the proceeds of sale of a number of vehicles and a plot of land.
There was a further deposit of US$6,500 on 14 June 2013 in the Access account. Ms Taiga made a payment to her daughter the same day of US$6,500. In her first statement Ms Taiga says that the US$6,500 may have been a loan from a family member intended for her daughter.
Ms Taiga received US$1,000 on 14 September 2015 from Eastwise Trading Ltd; US$10,000 on 18 December 2017 from ICIL; and US$10,000 on 27 June 2018, also from ICIL. Eastwise and ICIL are associated companies of P&ID.
There were payments of EUR 500 on each of 1 March and 25 March 2019 from ICIL. The EFCC uncovered these on 2 March 2020.
Mr Cahill says he has made further transfers to Ms Taiga since she was released from custody, but there is no information about how these payments were made and in what amount.
Ms Taiga’s daughter
As a result of its application in New York under 28 USC § 1782(a) in March this year, Nigeria discovered payments to Ms Taiga’s daughter of US$4,969.50 on 30 December 2009 and US$5,000 on 31 January 2012 respectively. Their source was companies associated with Messrs Quinn and Cahill, Marshpearl Ltd and Kristholm Ltd respectively.
Mr Tijani, member of the Ministry’s technical committee at time of GSPA
In addition to the US$50,000 cash which Mr Tijani says he was given as a gift in April 2009 – described shortly - there was a payment of some US$30,000 by SESFTF Progress Limited (a company controlled by Messrs Quinn and Cahill) to Conserve Oil
Limited (“Conserve Oil”) (a company associated with Mr Tijani). In addition, Lurgi (a company associated with P&ID) paid Mr Tijani NGN 3,440,000 (approximately
£15,310) on 3 April 2014. The same day Mr Tijani was paid NGN 4,350,000 by Conserve Oil. A year later, on 22 April 2015, he was paid NGN 4,000,000 (approximately £13,375) by Lurgi.
Ibrahim Dikko, Ms Taiga’s successor as legal adviser to the Ministry
Mr Quinn offered him US$2,000 in cash to attend the International Bar Conference in Dublin, which he accepted (although he does not appear to have attended).
Ms Adelore and Mr Oguine, legal directors at the Ministry and NNPC respectively
Already mentioned are the payments of US$100,000 to each of Ms Adelore and Mr Oguine by Mr Shasore on 18 November 2014 (Ms Adelore) and in 2014/2015 (Mr Oguine) respectively.
Other payments
Nigeria also relies on the payments into the bank accounts of Dr Lukman and Dr Ibrahim, referred to earlier. Nigeria states that their source is unknown at this point.
In addition to these specific payments, Nigeria also points to a spike in withdrawals from ICIL Nigeria’s bank account in Q2 of 2008 and Q1 of 2010 by James Nolan, a long-time business associate of Messrs Quinn and Cahill, and by ICIL’s accountant,
Mr Anekperechi Nworgu. In total these amounted to US$770,000 and NGN 15,000,000 (approximately £122,000) and were mainly in cash.
Witness statements
There are some 34 witness statements before the court, including eight from the Attorney General, Mr Malami. At this point, I offer brief summaries of what I see as the key statements and those which require mention in fairness to their deponents.
Ms Taiga
As we have seen, Ms Taiga was legal adviser to the Ministry at time of GSPA. In her first statement she says that at no time did she provide illegitimate assistance to P&ID. She provided legal assistance to her Ministry and did not negotiate the commercial terms of contracts, and that included the GSPA. She witnessed Dr Lukman’s signature, but that was routine. She was not responsible for ensuring compliance with public procurement or other legislation. As far as she was aware other ministries and departments were aware of the GSPA. The GSPA appeared a perfectly legitimate contract.
After she retired in September 2010, she says, she remained in touch with Mr Quinn. The payments which Mr Cahill made to her between 2015 and 2019 were as a favour, and at her request, to meet medical expenses. As regards the payment of US$10,400 into her Access bank account on 19 and 20 August 2010, Ms Taiga says this cash may well have come from the sale of a car or property from her late mother’s estate. Ms Taiga says that the US$6,500 deposited on 14 June 2013 may have been a loan from a family member intended for her daughter, not from Messrs Quinn or Cahill or anyone associated with P&ID.
In her second statement, Ms Taiga clarifies what she had previously said about the deposit in her bank account on 19 and 20 August 2010 and explains that it represented the proceeds of sale of a number of vehicles and a plot of land. As to the payments to her daughter in December 2009 and January 2012 by companies associated with Messrs Quinn and Cahill, she says that they provided financial support for private medical treatment in London and had nothing to do with the GSPA.
Mr Tijani
Mr Tijani was a member of the Ministry’s technical committee until he left in January 2011 to become (until 2015) the Commissioner of Energy and Mineral Resources in Lagos State.
In his first statement to the court, Mr Tijani states that he was chairman of the technical committee to review P&ID’s proposal. He says that in early 2009 he attended an unusual meeting in the office of Dr Lukman, the Minister of Petroleum Resources at the time. Mr Quinn, and a colleague, Neil Hitchcock, were there. Dr Lukman directed him to recommend P&ID’s project. After the meeting Mr Hitchcock dropped a black bag into his car, describing it as a “gift” and that they normally took care of their friends. It contained US$50,000 in cash.
Mr Tijani explains that as chairman of the technical committee he had the responsibility for assessing the project and that his recommendation was mostly binding on the technical side. He states that there were serious concerns about the project, including P&ID’s lack of a track record in this area, its failure to respond to the availability of wet gas for the project, which had not been properly investigated by the time the GSPA was executed (which the technical committee learnt about only after the event). Throughout the process the contract was withheld from the Minister responsible for gas resources, Mr Odein Ajumogobia. In approving the project, the committee overlooked the deficiencies because of Dr Lukman’s direction.
Mr Tijani adds that shortly after the GSPA was signed there was a meeting to discuss gas flaring issues in the Calabar region but nobody at the meeting was aware that a contract for a gas processing plant in the area had been signed and Dr Lukman kept silent about it.
In his statement, Mr Tijani confirms the bribes outlined earlier in the judgment. The payment of US$30,000 to Conserve Oil on 17 October 2013 was intended for him personally; the two payments of NGN 3,440,000 and NGN 4,350,000 on 3 April 2014 from Lurgi and Conserve Oil were intended as P&ID’s contributions to his son’s wedding (the second being funded out of an earlier payment by Lurgi to Conserve Oil on 10 March 2014).
Mr Tijani says that none of these payments were for services rendered by Conserve
Oil in connection with the “Bonga Audit” project. He was not involved with that project beyond making the initial recommendation of Conserve Oil, the company of his close friend from childhood, Mr Tunde Odebunmi. It was only later when he retired from his post as the Lagos State Energy and Mineral Resources Commissioner in May 2015 that he acquired an interest in Conserve Oil.
Mr Cahill’s statements
Mr Cahill was Mr Quinn’s business partner and co-founder of P&ID. For the purposes of the proceedings before the court Mr Cahill has given two statements. He denies that the GSPA or the Awards were procured by fraud, corruption or other illegal conduct.
In his first statement he accepts at paragraph 50 that the costs sunk in the preparatory work, referred to in paragraph 47 of Mr Quinn’s statement, were funded by Tita-Kuru. However, because Nigeria never challenged that part of Mr Quinn’s evidence it was not a contentious issue in the arbitration. As regards finance for the GSPA, Mr Cahill states at paragraph 80:
“It was never intended that the finance for the entire project would come from spare cash which [Mr Quinn] and I might have…we intended to fund the project with our own money to the point at which it became bankable, and thereafter we would raise finances…P&ID had been incorporated in the BVI in part to be an entity which would be attractive to lenders – a ‘bankable’ proposition. We were comfortable with the notion that the General [Danjuma] might be the source of such funding, but we were also nurturing interest from our discussions with other potential funders.”
In his second statement, Mr Cahill adds that when Mr Quinn said in his witness statement for the arbitration that the Cross River State Government had approved the land for the GSPA plant, that was accurate; Mr Quinn had not said that P&ID had bought the land.
Regarding the payments which Nigeria says are bribes, Mr Cahill says in his first statement that Mr Quinn and he became friendly with Ms Taiga when she was in the Defence ministry. He knew nothing about the deposit of US$10,400 in her bank account in August 2010. After she retired as a civil servant, Mr Cahill said, she would telephone him during Mr Quinn’s long illness and he was happy to provide her with support.
Mr Cahill states that he arranged for Ms Taiga to receive US$1000 through one of his companies, Eastwise Trading Ltd in September 2015. When she had a bad fall in late 2017, he made two payments through ICIL, each of US$10,000, on 18 December 2017 and 27 June 2018. They were not large amounts to him and intended for an old friend needing to meet medical needs. There were two further payments of US$500 each in March 2019, which his (Mr Cahill’s) assistant made, possibly for medical expenses. Mr Cahill adds that he provided further (unspecified) assistance to Ms Taiga for legal and other expenses after her release from arrest in September 2019.
In his first statement Mr Cahill denies the “black bag” cash payment of US$50,000 to Mr Tijani allegedly made in April 2009. Further, he adds, Mr Tijani was not remotely critical to obtaining the GSPA. As to the payments to Mr Tijani and Conserve Oil, these were for the services provided to Lurgi in obtaining technical personnel for the “Bonga Audit” project in 2013. Payment had been made of US$30,000 in October 2013 from another company he controlled, SESFTF Progress Ltd, since Lurgi had a joint account and payment (which Mr Tijani was insisting on) might be delayed. The Bonga Audit work was completed by the end of 2014.
In his second statement, Mr Cahill says that they chose Mr Tijani to assist with the Bonga Audit given his former membership of the technical committee of the Ministry and his extensive experience in the petroleum industry. The payment of N4,350,000 in March 2014 was to Conserve Oil for services rendered; he did not know whether it was then paid to Mr Tijani, although it would not surprise him since Conserve Oil was his company. Mr Cahill cannot recall the two payments of some US$30,000 made to Mr Tijani personally on 3 April 2014 and 22 April 2015, but he had no doubt that they were for Bonga Audit work and it was entirely possible that they were bonus payments.
As for the payments to Ms Taiga’s daughter of US$4,969.50 and US$5,000 in
December 2009 and January 2012, which the Nigerian authorities had recently learnt
about in the US, he had been told by someone working for ICIL at the time that he recalled they would be to help Ms Taiga with her medical expenses. They would have been authorised by Mr Quinn, who was the type of person who would always want to assist a friend.
The payment to Mr Dikko, explains Mr Cahill, would have been Mr Quinn’s hometown pride, with the IBA conference occurring in Dublin.
Mr Cahill explains in his second statement that during the negotiation process of the GSPA, in response to inquiries about progress, government officials would occasionally provide an update and from time to time documents. That included Dr Ibrahim, who was the likely source of an internal Ministry memorandum referred to in Mr Quinn’s witness statement for the arbitration.
Mr Nolan
Mr Nolan has worked with Messrs Quinn and Cahill for many years. In his first statement he attributes the spikes in ICIL’s cash withdrawals in 2008 and 2010 to Nigeria being a cash economy and to the need for cash for foreign exchange transactions on the parallel market. He also refers to cash being required for salaries, contractor payments, accommodation, travel and so on in relation to ICIL’s various projects in Nigeria.
Ramatu Lukman
Ramatu Lukman is the daughter of Dr Lukman, who was Minister of Petroleum Resources at the time of the GSPA and who died in 2014. She refers to Dr Lukman’s distinguished career, both in Nigeria and internationally. She states that he was a devoted public servant, of the highest integrity and would never have taken a bribe. As to the deposits of US$10,000 in 2009 in the GT Bank accounts, she says that may have been her father bringing relatively modest amounts of cash into Nigeria, as he was permitted to do, to help with the costs of living when he was there.
Legal framework
Position prior to award
Section 73 of the 1996 Act governs the position before an award is published: it has no relevance to the conduct of the party from that moment onwards: Merkin and Flannery on the Arbitration Act 1996 (6th edn) at [73.7]. Under it parties lose their right to object to a serious irregularity like fraud unless they raise the matter “forthwith” and can show that, at the time they took part or continued to take part in the proceedings, they did not know and could not with reasonable diligence have discovered the grounds for their objection.
In Sumakan Ltd v Commonwealth Secretariat [2007] EWCA Civ 1148, [2008] 2 All ER (Comm) 175 the Court of Appeal agreed with Toulson J that it was wrong to construe section 73 to hold that a person could with reasonable diligence have discovered facts which it neither knew nor believed nor had grounds to suspect: [36], [38], [62].
Extending time and the Kalmneft factors
Section 70(3) of the 1996 Act applies a 28 day time limit to an application or appeal under sections 67, 68 or 69. As a result of section 80(5) the court has discretion to extend the time limit. Colman J considered the background to this discretion in AOOT Kalmneft v Glencore [2001] 2 All E.R. (Comm) 577, [2002] 1 Lloyd’s Rep 128 – a case of an alleged procedural irregularity – and continued:
“[59] Accordingly, although each case terms on its own facts, the following considerations are, in my judgment, likely to be material:
(i) the length of the delay;
(ii) whether, in permitting the time limit to expire and the subsequent delay to occur, the party was acting reasonably in all the circumstances;
(iii) whether the respondent to the application or the arbitrator caused or contributed to the delay;
(iv) whether the respondent to the application would by reason of the delay suffer irremediable prejudice in addition to the mere loss of time if the application were permitted to proceed;
(v) whether the arbitration has continued during the period of delay and, if so, what impact on the progress of the arbitration or the costs incurred in respect of the determination of the application by the court might now have.
(vi) the strength of the application;
(vii) whether in the broadest sense it would be unfair to the applicant for him to be denied the opportunity of having the application determined.”
The Kalmneft factors and (i)-(iii) as primary factors
Later courts have regularly applied the so-called Kalmneft factors. In Terna Bahrain Holding Company WLL v Bin Kamil Al Shamsi [2012] EWHC 3283 (Comm), [2013] 1 Lloyd's Rep 86 Popplewell J stated them in a slightly refined form ([27]) and some courts have used these. The Kalmneft factors have been regarded as exhausting the considerations bearing on the exercise of the discretion to extend time.
In Nagusina Naviera v Allied Maritime Inc [2002] EWCA Civ 1147, [2003] 2 CLC 1, the Court of Appeal held that a judge’s exercise of discretion refusing to extend the time for service of an arbitration appeal under section 1(2) of the Arbitration Act 1979 could not be faulted. One of the submissions the court considered was that, although made under different provisions, the judge had not considered all the Kalmneft factors. At paragraph [39] Mance LJ (with whom Simon Brown and Latham LJJ agreed) said the judge had well in mind as primary factors those which in Kalmneft were factors (i)–(iii).
In his discussion of what in Kalmneft is factor (vi), Mance LJ thought it material that the case was not one where the appellants’ challenge was “so strong that it would obviously be a hardship for them not to be able to pursue it”: [41]. As to factor (vii),
he said that considerations of overall justice and fairness had always to be viewed in the particular context that Parliament and the courts had repeatedly emphasised the importance of finality and time limits for any court intervention in the arbitration process: [42].
Later courts have taken Mance LJ’s remarks in Nagusina as determining that factors (i)–(iii) are primary factors. Thus in L Brown & Sons Ltd v Crosby Homes (North West) Ltd [2008] EWHC 817 (TCC), [2008] BLR 366, Akenhead J said that the weight to be given to factor (vi) (the strength of the section 68 application) was not a primary factor, but “an intrinsically weak case will count against the application for extension whilst a strong case would positively assist the application”: [32 (c)]. Among other examples is Daewoo Shipbuilding v Songa Offshore Equinox [2018] EWHC 538 (Comm), [2018] 1 Lloyd's Rep 44, [89], per Bryan J.
However, in Ali Allawi v The Islamic Republic of Pakistan [2019] EWHC 430 (Comm), Carr J said:
“[47] For my part I do not read that judgment [Nagusina] as authority for the proposition that the first three factors are necessarily of more significance than any others. What weight each factor is to be attributed will depend on the facts of each case. All factors are relevant for consideration.”
If it were necessary, I would regard Carr J’s approach as correct. In my view her Ladyship’s approach is consistent with the judicial power being exercised, a discretion, so that the weight given to each Kalmneft factor must vary with the context. As Colman J stated in the original enunciation of the factors, “each case turns on its own facts”.
Mance LJ explained in Nagusina that Parliament and the courts had repeatedly emphasised the importance of finality and time limits in arbitration. Certainly section 1(a) of the 1996 Act states as a general principle that the object of arbitration is the resolution of disputes without unnecessary delay, and section 1(c) states nonintervention by the courts as another general principle. These point in favour of the importance of factors (i)-(iii). However, as general principles section 1 also refers to the fair resolution of disputes (sub-section (a)), and to party autonomy, subject only to public interest safeguards (sub-section (b)). It may have been that Carr J had these other general principles in mind in her analysis of the potential importance of the Kalmneft factors (iv)-(vii), depending on the circumstances.
Factors (i)-(iii): extent and reasons for delay
In Kalmneft [2001] 2 All E.R. (Comm) 577, [2002] 1 Lloyd’s Rep 128, Colman J emphasised that the relatively short period of time for making an application for relief under sections 67 and 68 reflected the principle of finality; parties had to live with an award unless they moved with great expedition: [52]. This need for expedition identified by Colman J recurs in the case law.
Important in this regard is Terna Bahrain Holding Company WLL v Bin Kamil Al Shamsi [2012] EWHC 3283 (Comm), [2013] 1 Lloyd's Rep 86. There Popplewell J refused to extend time to challenge an award because the applicant would in any event have failed in its serious irregularity challenge. However, he considered whether an extension would have been refused as a matter of discretion. From the authorities he derived the following principles governing an extension of time:
“[27]…Section 70(3) of the Act requires challenges to an award under sections 67 and 68 to be brought within 28 days. This relatively short period of time reflects the principle of speedy finality which underpins the Act, and which is enshrined in section 1(a). The party seeking an extension must therefore show that the interests of justice require an exceptional departure from the timetable laid down by the Act. Any significant delay beyond 28 days is to be regarded as inimical to the policy of the Act.”
Popplewell J then restated the Kalmneft factors and made four observations. First, delay had to be judged against the yardstick of the 28 days provided for in the Act: a delay measured even in days was significant, one measured in many weeks or in months was substantial: [28]. He continued:
“[29] Secondly, factor (ii) involves an investigation into the reasons for the delay… [W]here the evidence is consistent with laxity, incompetence or honest mistake on the one hand, and a deliberate informed choice on the other, an applicant's failure to adduce evidence that the true explanation is the former can legitimately give rise to the inference that it is the latter.
[30] Thirdly, factor (ii) is couched in terms of whether the party who has allowed the time to expire has acted reasonably. This encompasses the question whether the party has acted intentionally in making an informed choice to delay making the application…[I]n cases of intentional non-compliance with time limits, a public interest is engaged which is distinct from the private rights of the parties. There is a public interest in litigants before the English Court treating the Court's procedures as rules to be complied with, rather than deliberately ignored for perceived personal advantage.
[31] Fourthly, the Court's approach to the strength of the challenge application will depend upon the procedural circumstances in which the issue arises. On an application for an extension of time, the Court will not normally conduct a substantial investigation into the merits of the challenge application, since to do so would defeat the purposes of the Act. However, if the Court can see on the material before it that the challenge involves an intrinsically weak case, it will count against the application for an extension, whilst an apparently strong case will assist the application.”
At paragraph [32] Popplewell J then considered cases where the court was examining an extension of time when also considering the substantive issue (what could be described as a rolled-up hearing). As regards cases like the present, where by contrast the extension of time is being heard as a preliminary issue, he said:
[33]…[W]here the court can determine that the challenge will succeed, if allowed to proceed by the grant of an extension of time, that may be a powerful factor in favour of the grant of an extension, at least in cases of a challenge pursuant to s. 68. In such cases the court will be satisfied that there has been a serious irregularity giving rise to substantial injustice in relation to the dispute adjudicated upon in the award. Given the high threshold which this involves, the other factors which fall to be weighed in the balance must be seen in the context of the applicant suffering substantial injustice in respect of the underlying dispute by being deprived of the opportunity to make his challenge if an extension of time is refused. Where the delay is due to incompetence, laxity or mistake and measured in weeks or a few months, rather than years, the fact that the court has concluded that the s. 68 challenge will succeed may well be sufficient to justify an extension of time. The position may be otherwise, however, if the delay is the result of a deliberate decision made because of some perceived advantage.”
After canvassing the circumstances, Popplewell J concluded that the 17 weeks delay in that case was for deliberate, tactical advantage, and culpability for it was very high: [74]. The principle of finality in the Act would be undermined if parties could deliberately delay for a tactical advantage and the court would not be sympathetic in such cases: [82]. That was so even for an applicant who has good grounds for challenging the award: [83].
Fraud and the Kalmneft factors
Relevant to the court’s discretion in deciding whether to grant an extension of time is the strength of the applicant’s case on the merits, factor (vi).
In brief, section 68(1) of the 1996 Act provides that an arbitral award may be set aside on the grounds of a serious irregularity affecting the tribunal, the proceedings or the award. Under section 68(2) a serious irregularity means one which causes substantial injustice to the applicant and which is listed in the sub-section, including (g) “the award being obtained by fraud or the award or the way in which it was procured being contrary to public policy”.
There is a high hurdle to set aside awards under section 68, including for fraud and breach of public policy: see the synthesis in Stockman Interhold v Arricano Real
Estate [2017] EWHC 2909 (Comm), [2018] 1 Lloyd’s LR 135, [169], per Christopher Hancock QC, sitting as a Deputy High Court Judge.
Counsel cited eight cases involving extension applications where fraud was alleged. Of the cases where the application was refused, the applicant was either aware of the position, the fraud allegations were weak or both these considerations were in play. Thus in Thyssen Canada Ltd v Mariana Maritime SA [2005] EWHC 219 (Comm),
[2005] 1 Lloyd’s Rep 640, involving a five month delay, evidence of the alleged perjury was available to the appellant during the arbitration with reasonable diligence, but there was a deliberate tactical decision not to rely on it on since the new evidence could damage its own case: [35]. While expressing no overall view on the merits, Cooke J noted that the allegation of perjury in the case faced “obvious challenges”. “Whilst the strength of the application is one which the Court can take into account”, he said, “it is self-evident in the present case that there are extensive conflicts of evidence between the parties”: [56].
In DDT Trucks of North America Ltd v DDT Holdings Ltd [2007] EWHC 1542 (Comm) | [2007] 2 Lloyd's Rep 213 Cooke J had no difficulty in refusing an extension of 14/15 weeks (a “futile exercise”). The section 68 challenge was “bound to fail”, he held, because evidence of the alleged perjury was available to the appellant throughout but its lawyer had forgotten about it. In any event, the evidence was not so
strong that it could reasonably be expected to affect the outcome of the arbitration ([27]-[30]).
The position was similar in L Brown & Sons Ltd v Crosby Homes (North West) Ltd [2008] EWHC 817 (TCC), [2008] BLR 366 (documents allegedly withheld in first arbitration in possession of appellant before 28 day deadline expired; solicitor’s explanation for needing extra 66 days to draft the application unconvincing ([57]); in any event, fraud challenge “very much at the intrinsically weak end of the spectrum” ([81])); Colliers International Property Consultants v Colliers Jordan Lee Jafaar SDN BHD [2008] EWHC 1524 (Comm), [2008] 2 Lloyd's Rep 368 (no evidence (a) of the alleged fraud or (b) to show that it could not have been raised during arbitration ([32]); Nestor Maritime SA v Sea Anchor Shipping Co Ltd [2012] EWHC 996
(Comm), [2012] 2 Lloyd's Rep 144 (alleged fraud in technical evidence about ship’s thickness measurements reasonably discoverable sooner than the six months delay; in any event application under section 68(2)(g) at best extremely weak ([28], [54]).
The three remaining cases, where an extension was granted were, unlike the present, rolled up hearings so that the court was considering the exercise of its discretion to extend the time limit in the context of a full consideration of the merits. In Elektrim SA v Vivendi Universal SA [2007] EWHC 11 (Comm), [2007] 1 Lloyd’s Rep 693, the appellant alleged that a document had been fraudulently withheld in the arbitral proceedings. Although Aikens J held that there was no evidence of deliberate concealment, he held that it was reasonable to wait until the matter was investigated, then to make the extension application at the same time as the substantive challenge: [72].
Then in Chantiers de l’Atlantique SA v Gaztransport & Technigaz SAS [2011] EWHC 3383 (Comm) the allegation was that scientific evidence presented in the arbitration was fabricated and contradictory evidence deliberately withheld. Flaux J held that the deliberately misleading evidence did not have an effect on the tribunal’s decision: [296]. Given the significance of the allegations, he also held, it had been a responsible approach that the appellant should investigate the matter properly before making the application: [66].
Finally, in Celtic Bioenergy Ltd v Knowles Ltd [2017] EWHC 472 (TCC), [2017] 1 Lloyd's Rep 495, Jefford J granted the extension after a short delay in a case where there was a deliberate and “utterly misleading” withholding of information from the tribunal on significant issues in the case: [53].
Citing Elektrim and Chantiers cases, Russell on Arbitration, 24th ed, London, 2015 suggests that cases regarding alleged fraud under s.68(2)(g) are arguably treated as special cases for the purposes of granting an extension, “for if the relevant evidence comes to light after the award (as it necessarily has to for an arguable s.68(2)(g) application to be made) and is then investigated diligently by the applicant an extension of time would usually be granted.”
Relief from sanctions
Nigeria requires relief from sanctions for adducing new evidence in response to P&ID’s enforcement application after the deadline directed by Bryan J in his Order dated 21 October 2018. The test for granting relief from sanctions is the three-stage
test in Denton v TH White [2014] EWCA Civ 906, [2014] 1 WLR 3926. It was common ground that the relief from sanctions application would stand or fall with Nigeria’s extension of time application, although I was referred to Lord Neuberger’s judgment in Prince Abdulaziz v Apex Global Management Ltd [2014] UKSC 64, [2014] 1 WLR 4495, that the strength of the parties' cases would generally be irrelevant when the court was considering whether to grant relief from sanctions: [29].
The impact of Takhar [2019] UKSC 13
In Takhar v Gracefield Developments Ltd [2019] UKSC 13, [2020] AC 450 the Supreme Court allowed an action to proceed to set aside an earlier judgment on the basis of fraud. At the first trial, although Mrs Takhar had suspected fraud, she had not alleged it, and only later obtained evidence that a key document had, in fact, being forged. Lord Kerr for the majority held that where a party seeks to set aside a judgment on grounds of fraud, it is not necessary to show that the evidence of fraud could reasonably have been uncovered sooner: [54]. Two possible exceptions were where fraud has already been argued at the trial and where a deliberate decision had been taken not to investigate the possibility of fraud in advance of the first trial, even if fraud had been suspected: [55]. Lord Sumption agreed, in particular that a claimant who had deliberately decided not to investigate a suspected fraud might be shut out: [63].
In considering Takhar in Elu v Floorweald Ltd [2020] EWHC 1222, Linden J held that it did not apply in situations where a party positively believes that a claim is fraudulent and has evidence to prove it: [156(vi)]. That was a case where Ms Elu’s “new” evidence of fraud was in her possession at the time of the original trial but she had not put it before the court.
For Nigeria, Mr Howard QC submitted that Takhar decided that in previous decisions English law had taken the wrong turn in requiring the exercise of reasonable diligence regarding an abuse of process and that, as a general principle, a fraudster cannot contend that a person failed to exercise reasonable diligence to uncover a fraud. He contended that, because it is a general principle of English law, Takhar applies equally to challenges to set-aside an arbitral award under section 68 of the 1996 Act. In other words, an applicant is not required to prove that it could not reasonably have discovered a fraud sooner in an arbitration.
Mr Mill’s submission for P&ID was that Takhar had no application to arbitrations. Before the award, section 73(1) of the 1996 Act governed, and that imposed a reasonable diligence test as a matter of statute. After the award the principles of finality and non-intervention in section 1 of the Act applied, as did section 70(3) with its 28 day time limit for any application under sections 67, 68 and 69 of the Act, including a challenge based on fraud under section 68(2)(g).
The “fraud unravels all” cases on which Lord Kerr relied, continued Mr Mill, preceded the 1996 Act. The drafters of that Act must have been aware of them, but notwithstanding that did not make any exception in cases of fraud. In examining the general principles applicable to setting aside a judgment, the Supreme Court in Takhar cannot be supposed to be addressing the limited grounds in sections 67 and 68 of the 1996 Act to set aside an arbitral award on grounds of fraud.
If it had been necessary to decide the issue, it seems to me that Mr Howard has the best of the arguments. It is a fundamental principle of our law that, as Lord Bingham said in HIH Casualty and General Insurance Ltd v Chase Manhattan Bank [2003] UKHL 6, [2003] 2 Lloyd's Rep 61 - referring to what Rix LJ had said in the Court of Appeal - that fraud is a thing apart, it unravels all: [15]. There seems to be no reason why the finality of arbitration awards should be afforded greater importance than the finality of judgments in circumstances of fraud. The statutory bar in section 73 is limited to irregularities discoverable during the arbitration. Otherwise, the effect of section 81(1) of the Act is to preserve the right to challenge the enforcement of an award on public policy grounds under the common law. As Mr Howard contended, there is no reason to interpret the Act so that Takhar is confined to common law public policy challenges and not to those under section 68(2)(g).
Fraud in the GSPA and the arbitration
Nigeria’s case in brief is that it has established a prima facie case of fraud against P&ID, which justifies the extension of time and will give it the opportunity to establish at trial its full ramifications for the arbitration.
Although referring to other aspects of the alleged fraud, Mr Howard QC concentrated on three aspects: first, that P&ID procured the GSPA by paying bribes to Nigerian officials; secondly, that Mr Quinn gave perjured evidence to the Tribunal to give the false impression that P&ID was able and willing to perform the GSPA; and thirdly, that Nigeria’s counsel in the arbitration, Mr Shasore, dishonestly failed to challenge Mr Quinn’s perjured evidence or to seek disclosure from P&ID such that the Tribunal had no choice but to find in its favour.
Nigeria’s challenges under sections 67 and 68(2)(g) of the 1996 Act are wider than this; for example, the section 67 jurisdictional challenge is based on the allegation that clause 20 of the GSPA, which differs from the normal Nigerian model clause for arbitration, was itself procured by fraud and was part of P&ID’s overall fraudulent scheme. However, I focus on Mr Howard’s three main points.
In his submissions for P&ID, Mr Mill QC said that, at best, I could not conclude one way or the other whether there was a case of fraud; at worst, I would conclude that the case was weak. The fraud alleged was, in Mr Mill’s submission, startlingly ambitious, beginning with the procurement of the GSPA though bribery, continuing with the fabricated dispute and arbitration and finishing years later with the enforcement and execution of the award and the division of the spoils.
On Nigeria’s case, Mr Mill emphasised, the fraud was sustained over many years, and involved many different persons and interests. That, he submitted, told against the case Nigeria had advanced. This was a genuine, not a fabricated commercial dispute, he underlined, which had properly been submitted to arbitration and been dealt with in the arbitration in a perfectly straightforward manner.
Negotiation of the GSPA
Mr Howard’s case for Nigeria was that P&ID procured the GSPA by paying bribes to Nigerian officials, including Ms Taiga and Mr Tijani. In return, these officials overlooked the shortcomings of P&ID’s bid. It was only recently, with the successful application in New York under 28 USC § 1782(a), that evidence came to light that a payment was made by P&ID to Ms Taiga’s daughter just before the GSPA was signed.
Yet, Mr Howard submitted, P&ID tried before the New York judge to prevent this evidence from being used in these proceedings. Until then, Mr Howard added, P&ID’s evidence had been that payments to Ms Taiga occurred well after the GSPA was concluded. In any event, Mr Howard contended, the bribes P&ID paid after the GSPA, indeed until very recently in Ms Taiga’s case, were in return for the continued silence about the fraud.
In addition to the bribes identified for Ms Taiga and Mr Tijani, Mr Howard submitted, there was evidence of supporting payments to other corrupt officials, including the Minister for Petroleum Resources, Dr Lukman. There was the spike in cash withdrawals from ICIL’s bank account, around the time the GSPA was signed in 2010, totalling US$770,000 and NGN 15,000,000 (approximately £122,000). Mr Nolan’s explanation for this in his statement did not bear scrutiny; there was expert evidence that quite apart from money-lending considerations, the oil and gas sector did not operate in the informal sector. Mr Howard’s case was that it could be inferred, against the background of strong evidence of bribery and corruption by P&ID, that this cash was used to pay bribes to Nigerian officials, including Dr Lukman.
Mr Mill’s response to this was that following the entry into the GSPA, in the two years until the commencement of the arbitration, P&ID was pressing the government to implement its side of the bargain in forums which made it highly unlikely that all the participants were a party to the alleged fraud.
As to Dr Lukman, said Mr Mill, he was a distinguished Nigerian and an international statesman. There was no credible evidence in support of his involvement in a fraudulent scheme with P&ID. There was no link between P&ID and the payments into his bank accounts which the EFCC had identified. His daughter had given an acceptable explanation for them in her statement (referred to earlier in the judgment).
With Ms Taiga, Mr Mill’s submission was that it was impossible to reach any conclusion on the payments to her. The one suspicious payment was in 2009 but, Mr Mill submitted, an explanation had been given that it was for medical expenses. Ms Taiga’s daughter had also explained that in Nigeria it was common to make requests to friends in circumstances where a person was facing difficulties, as with her mother’s medical condition. Mr Mill submitted that the later payments to Ms Taiga were after she had retired so could have had no bearing on the execution of the GSPA. In any event good reasons had been given, he said: Ms Taiga had complex and serious medical conditions and her friends at P&ID had agreed to help.
As for payments to Mr Tijani other than the alleged US$50,000 black bag payment - for which, Mr Mill asserted, there was no evidence whatsoever - Mr Mill recalled that they were made well after the GSPA was agreed and Mr Tijani’s involvement on the technical committee had ceased. Nowhere, adds Mr Mill, does Mr Tijani himself explain these later payments on the grounds that they were designed to buy his silence. In Mr Mill’s submission, there was contemporaneous evidence that the payments were for the Bonga Audit project, work which was in fact done. It was not possible for me, Mr Mill contended, to come to any conclusion on the Bonga Audit payments one way or the other.
In my view there is a strong prima facie case that the GSPA was procured by bribery. It is sufficient to focus on the two senior officials whose positions ensured its safe passage by giving the requisite approvals. First, there is Ms Taiga, who was the senior legal adviser to the Ministry at the time of the GSPA and recommended its execution. In their second statements both Ms Taiga and Mr Cahill accept that payments were made to her by P&ID, but their account is that they were intended for Ms Taiga’s medical expenses. There is no supporting evidence for this, such as contemporaneous communications between P&ID and Ms Taiga referring to her medical needs.
In any event, whether these payments were for medical or other expenses, as the Attorney General explains in his seventh statement, benefits received by public officials from individuals holding or seeking to obtain a contract are assumed to be bribes under the Corrupt Practices and Other Related Offences Act 2000 and the Nigerian Constitution. Further, as he explains in his sixth statement, Ms Taiga’s annual salary was US$5,000. The total amount paid to Ms Taiga from 2009 was many times that amount.
There is also the point Mr Howard highlighted, that Ms Taiga and Mr Cahill did not mention any payments to her before 2015, after her retirement. Earlier this year, following the applications in New York under 28 USC § 1782(a), the payments to Ms
Taiga’s daughter of US$4,969.50 and US$5,000 on 30 December 2009 and 31 January 2012 respectively, were identified. The first payment is especially significant, since it was 11 days before the GSPA was signed. As I explained earlier, in the New York proceedings P&ID did seek to prevent Nigeria’s use of that information in these proceedings.
Then there were the payments to Mr Tijani, chairman of the committee in the Ministry assessing P&ID, which he admits he received. Mr Tijani accepts that the technical committee, which he chaired, overlooked deficiencies in P&ID’s bid, although he attributes his own behaviour to the direction that Dr Lukman had given him. Even if I accept Mr Mill’s submission that it is impossible to reach any conclusion in relation to some payments to Mr Tijani, there is no explanation as to why the payments of US$30,000 in April 2015 went to Mr Tijani directly and after the Bonga Audit was completed. There is nothing to support Mr Cahill’s story that these might be bonus payments. Moreover, there is Mr Tijani’s own account that the P&ID payments had nothing to do with that project.
Mr Quinn’s evidence and P&ID’s ability to perform the contract
Mr Howard’s case was that Mr Quinn gave perjured evidence to the Tribunal that P&ID had (i) invested US$40 million in the project and had completed 90 percent of relevant engineering design work (including 100 folders of technical documents); (ii) put in place all necessary project finance; and (iii) acquired a plot of land for the gas stripping. Contrary to this evidence, he contended, P&ID was never willing and able to perform the GSPA. Yet, he continued, P&ID’s readiness and ability to finance the project and to perform the GSPA were critical to its successful claim in the arbitration to have suffered loss by reason of its repudiation.
First, then, the US$40 million spent on the project and the almost completed engineering design work. Mr Howard submitted that this was a lie in light of the letter to the EFCC from Tita-Kuru of 20 September 2019, stating that it had paid the sum of $40 million to P&ID for the development of the engineering work, design and off-take consultancy services for the Badagry project, Project Alpha, not P&ID’s Calabar project in a different part of the country. The letter stated that P&ID used this work in their presentation to the Ministry. The clear, and most likely, inference, Mr Howard contended, was that apart from Tita-Kuru’s work product nothing else was ever produced and that P&ID would never have been in a position to perform the contract.
Drawing in part on the BRG expert report for the quantum hearing, Mr Mill’s submission was that P&ID and those working with it had undertaken a very considerable amount of work such that they were in an advanced state of preparation for building the facility. Mr Quinn never said explicitly that P&ID had spent the US$40 million, only that it had been spent. In Mr Mill’s submission it did not matter who had spent the money; the Tita-Kuru letter confirmed that it had been spent. The issue was P&ID’s state of preparedness. The fact was that the work had been done; that was all Mr Quinn was saying.
In my view there are serious difficulties with Mr Mill’s submission. First, that is not the impression Mr Quinn conveys at paragraph 47, and later at paragraph 110 of his statement, both quoted earlier in the judgment. At paragraph 47 Mr Quinn stated that in the first two years of the project he estimated that the total costs sunk into the preparatory work were in excess of US$40 million, which had involved commissioning a number of specialist companies, and that there were about 100 volumes of documentation. On my reading of the paragraphs it is P&ID which is alleged to have done all this. (I note in passing that in other correspondence referred to earlier Mr Quinn refers to “our expenditure”.)
Next, Mr Cahill does not give unequivocal support to Mr Mill’s submission. In his first statement to this court at paragraph 50, Mr Cahill accepts that the cost of the preparatory work referred to in paragraph 47 of Mr Quinn’s evidence was funded by Tita-Kuru, not P&ID, adding (in my view significantly) that Nigeria never challenged this part of Mr Quinn’s evidence and it was not a contentious issue in the arbitration.
Further, none of the engineering drawings or 100 volumes Mr Quinn referred to in his statement have been produced, apart from the power-point presentation of October
That was the only contemporaneous document exhibited to Mr Quinn’s statement and used for the BRG report. As I have explained, the two computer assisted designs in the presentation were from General Danjuma’s Project Alpha and marked as such.
As to finance, Mr Quinn said in his statement that all of the project finance was in place. (P&ID’s evidence before the Tribunal was that capital expenditure of some $500 million was needed to construct the gas processing plant envisaged by the GSPA.) Mr Mill accepted that there may be a touch of hyperbole or an element of exaggeration in what Mr Quinn said but submitted that Mr Cahill would support the view that they had every reason to suppose that the funding would be available.
This will not do. On Mr Cahill’s evidence alone, Mr Quinn’s statement in this regard is false. At paragraph 80 of his first statement Mr Cahill says that he and Mr Quinn intended to fund the project with their own money to the point at which it became bankable. (Again I note in passing that in its letter to the President on 7 August 2008, P&ID had stated that it was willing itself to fund the entire US$700,000,000 for the facility.) In his statement, Mr Cahill adds that General Danjuma might be a source of funding, and that they were nurturing interest with other potential funders. There are no details of what nurturing had been undertaken, and with whom.
Finally, there is Mr Quinn’s statement at paragraph 109 that the site for the gas stripping plant had been “secured” from the Government of the Cross River State, and at paragraph 110 that a 50 hectare site had been “allocated”. On 11 February 2010 the Government of Cross River State had written to P&ID, confirming approval for a grant of land, subject to payment of NGN21,015,138 (about £44,500). In the letter of 4 September 2019, the state director of lands explained to the EFCC that since P&ID never paid for the land it was never allocated to it.
In his statement Mr Cahill concedes that although the land had not been bought, it had still been allocated, a point which Mr Mill underlined in his submissions. By itself Mr Quinn’s remark about the site being allocated would not have been serious. However, in context it is part of a piece with the falsities in other parts of the statement.
In my view Nigeria has established a strong prima facie case that Mr Quinn gave perjured evidence to the Tribunal to give the impression that P&ID was a legitimate business and was able and willing to perform the GSPA. P&ID then relied on that evidence before the Tribunal in the knowledge of its falsities.
Mr Shasore’s conduct of the arbitration
Mr Howard’s case was that in the first two stages of the arbitration its counsel, Mr Shasore, deliberately defended the case thinly such that the Tribunal had no choice but to find for P&ID. The reason was that he had colluded with P&ID, with the inevitable result that Nigeria would lose the case.
In advancing his case, Mr Howard pointed to various factors: Mr Shasore had advised a speedy settlement, as in his 17 July 2013 letter to the then Attorney General, without investigating the obvious line of defence that P&ID, a BVI company with no experience, assets or finance, would not perform. Next, Mr Shasore concealed his involvement from his own firm. Further, in the conduct of the arbitration he did not seek disclosure of any of the 100 files Mr Quinn referred to in his statement, relevant to the preparatory work P&ID was said to have performed. Finally, there was no useful evidence on the Nigerian side in Mr Oguine’s witness statement, which he drafted.
It was significant, Mr Howard submitted, that in the arbitration proceedings Mr Shasore failed to challenge Mr Quinn’s evidence of P&ID’s ability and willingness to perform the contract and the US$40 million said to have been expended. His attempt at cross-examination of Mr Quinn was bound to fail when he had not challenged anything significant in Mr Quinn’s statement, the issue of cross-examination was foreclosed at the case management hearing in which he participated, and Mr Quinn was dead (which he claimed not to know).
Then there were Mr Shasore’s reply submissions, added Mr Howard, where he wrongly asserted that his statement of disputed facts essentially challenged all the facts in Mr Quinn’s statement. Additionally, Mr Shasore dragged his feet when conduct of the arbitration was transferred from the Ministry to the Attorney General for the quantum stage. At the quantum stage, Mr Howard submitted, Nigeria’s new counsel, Mr Ayorinde, was precluded from reopening the matter. Not only did he not know of Mr Shasore’s behaviour, he had no basis to apply to reopen the Tribunal’s prior findings.
In response, Mr Mill submitted that it simply could not be said that this was a fabricated dispute, and Nigeria did not treat it as such. Through Mr Shasore Nigeria advanced what would have been a knock-out blow with its challenge on jurisdiction with an argument which even the Attorney General, Mr Malami, thought was a good one.
That was entirely inconsistent with the suggestion, said Mr Mill, that Mr Shasore was somehow conspiring with P&ID and putting up a sham defence for the sake of appearances. There was no evidence, submitted Mr Mill, to support Mr Howard’s speculation that Mr Shasore might have been corrupted, if not from the outset of the arbitration, certainly after the Jurisdiction Award.
The reality was, Mr Mill contended, that this was a genuine dispute which, given the language of the GSPA, Nigeria was hard-pressed to defend, but which it fought over a
number of years from its inception in August 2012 until the Final Award in January 2017. Mr Shasore’s conduct, and the Nigerian defence generally, were inconsistent with a deliberate plan to lose the case.
As to the liability hearing, submitted Mr Mill, Mr Shasore tried his hardest - having misapprehended the implications of Procedural Order No. 9, and the discussion at the case management conference - to get himself out of a hole. By reference to the transcript and the Tribunal’s reasons, Mr Mill also submitted that there was nothing to prevent Mr Ayorinde from reopening the matter at the quantum stage of the arbitration.
At one level I can see that in Mr Shasore’s favour it might be said that he did the best he could in circumstances where he had a difficult case and, at least for part of the time, faced a lack of instructions from the Ministry (as I have mentioned above). Albeit he did not seek discovery, he did advance the jurisdiction argument, and at the liability stage identified at short notice six facts in Mr Quinn’s statement which Nigeria wished to dispute (albeit that P&ID did not need to rely on them).
Moreover, it might be said that Mr Shasore took a number of points on liability, although the Tribunal dismissed them without too much difficulty. Whatever the cause it seemed to follow as a matter of course that at both the liability and quantum stage the Tribunal would accept Mr Quinn’s evidence as to the willingness and ability of P&ID to perform its part of the GSPA. As Mr Mill put it, Mr Shasore faced the timeless problem of advocates dealt a poor hand and making the best they could.
However, what persuades me of a prima facie case of dishonesty in Mr Shasore’s conduct of the arbitration are his payments of US$100,000 each to Ms Adelore and Mr Oguine. Ms Adelore occupied Ms Taiga’s position at the Ministry as the senior
lawyer, and Mr Oguine was her counterpart at the NNPC. Their salaries as public servants, according to the Attorney General, Mr Malami, were some US$5000 per annum.
Mr Mill submitted that these payments had nothing to do with P&ID. Moreover, Mr Shasore had volunteered the information about them to the EFCC and described them as gifts.
The argument that Mr Shasore volunteered the payments goes nowhere, since once the EFCC had information from the bank accounts it was difficult to deny them. As to Mr Shasore’s account that these were gifts, that does not seem to me a complete and honest explanation for why he should make these payments to these senior public servants.
Part of the picture is that after the payment to Ms Adelore, she wrote to the Ministry’s permanent secretary on 30 December 2014 recommending a settlement. We also saw that when the EFCC investigated in the first part of 2016, she was the source of information at the Ministry. I have also mentioned that Mr Oguine was charged with producing witnesses for Nigeria but instead put his name to a witness statement in May 2015 which the Tribunal said was of no assistance to its case. Moreover, with Mr Shasore, Ms Adelore and Mr Oguine comprised Nigeria’s settlement team in late 2014.
In the result there is a possibility that Mr Shasore had been corrupted. At the least I accept Mr Howard’s submission that there is a prima facie case that Mr Shasore made the payments to Ms Adelore and Mr Oguine to purchase their silence in relation to his conduct of the arbitration and settlement negotiations. There is therefore a prima facie case that the arbitration proceedings were tainted.
Conclusion of fraud
In my view Nigeria has established a strong prima facie case that the GSPA was procured by bribes paid to insiders as part of a larger scheme to defraud Nigeria.
There is also a strong prima facie case that P&ID’s main witness in the arbitration, Mr Quinn, gave perjured evidence to the Tribunal and that, contrary to that evidence, P&ID was not in the position to perform the contract. As to the Jurisdiction and Liability stages of the arbitration, there is a prima facie case that they were tainted by the conduct of Nigeria’s advocate, Mr Shasore.
Investigating the fraud
Mr Mill contended that Nigeria could not adequately explain the massive delay of nearly three years from the date of the Final Award in initiating the current proceedings. In particular, it could not discharge the burden of establishing that it did not know and could not with reasonable diligence have discovered the alleged fraud.
Mr Mill’s case was that the evidence which ultimately caused Nigeria to undertake the post-August 2019 investigation - following Butcher J’s judgment on enforcement - was available not later than the EFCC interim report in June 2016, before the Final
Award. Nothing new emerged between that report and August 2019. It was only after Butcher J’s decision that Nigeria acted with anything like reasonable diligence, but it still dragged its feet.
Mr Mill divided the time into three distinct periods: (i) the period after the appointment of Mr Malami as Attorney General on 11 November 2015 until the issue of the Final Award, 31 January 2017; (ii) the period between the Final Award to just after Butcher J handed down his enforcement judgment on 16 August 2019; and (iii) the period from then until the issue of the current claim on 5 December 2019. It is convenient to adopt that categorisation.
Period up to Final Award, 31 January 2017
As to the period before the Final Award on 31 January 2017, Mr Mill’s submission was that this delay meant Nigeria would be barred from its claim under section 73 of the 1996 Act. Mr Mill contended that Nigeria had ignored the recommendations of its lawyers and officials to investigate the circumstances surrounding the GSPA, and therefore had not exercised the reasonable diligence section 73 required to discover the grounds for its present objections to the Final Award.
Mr Mill highlighted that Stephenson Harwood had recommended on 1 February 2016 that the Ministry appoint a credible investigations company to inquire into P&ID. That was not done. Then the EFCC was commissioned to investigate in February 2016, but Nigeria did not follow the recommendation in its interim report of 16 June 2016 that a further detailed investigation take place. Instead, Nigeria pursued a policy of settlement.
In Mr Mill’s submission, given the EFCC’s remit, the Attorney General’s acknowledgment of endemic corruption in Nigeria, the description of the EFCC February-June 2016 investigation as concerned with conspiracy, abuse of office and misappropriation of public funds – all these meant the detailed investigation EFCC recommended would have encompassed a relatively straightforward inquiry into fraud, P&ID and its principals, and whether the key officials the report referred to, including Ms Taiga and Mr Tijani, had been bribed or corrupted. Consequently, summarised Mr Mill, Nigeria had not exercised reasonable diligence in investigating the fraud it now alleged.
It seems to me that Nigeria has made a good case that, at the time it took part or continued to take part in the arbitration, it did not know and could not with reasonable diligence have discovered the grounds it now advances. As Mr Howard submitted, it could not reasonably be expected that those now alleged as the key fraudsters - Messrs Quinn (until his death) and Cahill, the principals of P&ID - would have revealed their own fraud. In Mr Cahill’s statement for these proceedings, he added, Mr Cahill now acknowledges that Mr Quinn’s witness statement for the Tribunal contained serious inaccuracies (to put it no higher), but he and his legal representatives did not say anything at the time.
At the point of the Jurisdiction and Liability Awards the position was compounded if, as Mr Howard submits, Nigeria’s counsel, Mr Shasore, had been corrupted. Even if Mr Shasore had not been corrupted, I accept Mr Howard’s submission that Mr Shasore could not reasonably have been expected to discover if, as seems to be the case, that the GSPA was procured by bribes, and that P&ID’s plan from the outset
was to extract money from Nigeria through contrived settlement negotiations or arbitration.
When Mr Shasore was replaced for the quantum hearing and Final Award, I also accept Mr Howard’s submission that Nigeria’s new counsel, Mr Ayorinde would have no reason to suppose that Mr Quinn’s evidence to the Tribunal had been perjured, that P&ID was not a legitimate business which was ready and able to perform the GSPA, or that Mr Shasore was implicated in illegitimate payments to senior civil servants acting with him. Mr Ayorinde’s conduct of the arbitration in this regard is explicable.
To my mind there can be no criticism that Nigeria did not take up Stephenson
Harwood’s recommendation of appointing a private inquiry company; the EFCC is the statutory agency charged to undertake this type of investigation.
The EFCC inquired, but it found that the GSPA had been approved at a senior level, with Ms Taiga on the legal side and Mr Tijani on the technical committee. In other words, the GSPA had the cloak of legitimacy. The situation only changed with Mr Tijani’s statement to the EFCC early this year, accepting that he had waved the project through, despite its deficiencies.
In 2016 the EFCC had recommended further investigations surrounding the award of the contract and the key parties to it, but there was no suggestion in the report that bribery and corruption was at the forefront. Instead, the report concentrated on matters such as the capacity of P&ID to perform the GSPA.
In summary, this does not seem to me a case where Nigeria knew, believed or had grounds to suspect so as to have taken further steps as regards the fraud now alleged: Sumakan Ltd v Commonwealth Secretariat [2007] EWCA Civ 1148, [2008] 2 All ER (Comm) 175, [36], [38], [62]. In other words, it seems to me that at this stage Nigeria can rightly claim that it could not with reasonable diligence have ascertained the fraud.
Period between Final Award and Butcher J’s judgment, 20 August 2019
In advancing P&ID’s case on the period after the Final Award was issued, on 31 January 2017, until what he contended was the commencement of the fraud investigation in August 2019 - after Nigeria lost before Butcher J on enforcement of the Final Award - Mr Mill contended that Nigeria’s case that it proceeded with its inquiries with anything like reasonable diligence was risible. Instead, it took a deliberate decision not to investigate fraud but pursued settlement which, as the Attorney General accepted in his sixth witness statement, would likely be impeded by a criminal investigation.
In Mr Mill’s submission the correspondence from the Attorney General to the Vice President on 13, 17 and 29 March 2017 was telling. It had recommended attempts at settlement, and the Vice President had approved, but the scenario in these letters that the EFCC should be directed to undertake a discreet investigation of the matter into P&ID was dropped.
In other words, submitted Mr Mill, this was the deliberate decision leading to delay, clearly evidenced in the Curtis memorandum on 12 July 2018. Despite suspicions of
fraud - the Vice President’s “fraud on the nation” in June 2018 - Nigeria deliberately chose not to investigate the alleged fraud or launch a challenge to the Final Award.
Mr Mill accepted that the EFCC was commissioned to investigate in June 2018, but that was 17 months after the Final Award and prompted by the failure of the settlement negotiations and the US enforcement proceedings. That June investigation did not pursue matters with urgency or diligence in the 14 months until Butcher J’s judgment in August 2019. All that occurred was that the EFCC sent a limited number of letters asking various institutions for information.
In written submissions of 13 August 2020, following the hearing, Mr Mill referred to the newly released letter from the Attorney General, Mr Malami, to the President of 5 June 2020 about Mr Magu, acting head of the EFCC. He contended that it confirmed that P&ID’s account was correct, and that Mr Malami’s assertion in his seventh witness statement that after June 2018 the EFCC investigation moved with “urgency and expedition” was quite wrong. In Mr Mill’s submission, Mr Malami’s letter to the President on 4 August 2020, seeking to distinguish Mr Magu’s behaviour and that of the EFCC, did not bear scrutiny.
To my mind an initial difficulty with Mr Mill’s submissions is the contradiction they contain. On the one hand P&ID is saying that Nigeria should have investigated fraud more vigorously, but instead took a deliberate decision to pursue settlement, while at the same time asserting that no fraud existed. On P&ID’s own case there was nothing to investigate. Related to this point is that P&ID was presenting itself as a legitimate commercial company, able and willing to perform the GSPA, thwarted by the failure of Nigeria to provide wet gas, and justifiably engaging in arbitration and legal proceedings in London and New York with the assistance of an international law firm, global financial consultants and, from social media posting I was shown, it seems media consultants as well. Yet somehow the Nigerian authorities should have taken the decision to investigate fraud.
It is important not to interpret events in hindsight. Investigating fraud was not an EFCC recommendation in its 2016 interim report where, as we have seen, the focus was on matters such as the capacity of P&ID to perform the GSPA and the conduct of the Ministry’s technical committee. As to the activity after the Final Award was issued on 31 January 2017, the Attorney General stated in his letter of 13 March 2017 that loopholes might be discovered, mentioning fraud, technical grounds or a conflict of interest of the arbitrators. That in my view hardly indicated grounds to suspect fraud, rather an attempt to identify any possible avenue of challenge (any loophole).
Following P&ID’s enforcement application of 16 March 2018 there is the correspondence and meetings leading to the commissioning of the EFCC to inquire in June that year. As I observed in argument, the Vice President’s comment about “fraud on the nation” can be interpreted as a political statement from someone deeply concerned with the size of the Tribunal’s damages award but who, understandably, was not involved with the detail of the arbitration. In other words, the Vice President was not suggesting that the GSPA and the arbitration constituted, as Nigeria now submits, a massive fraud. In Kazakhstan Kagazy plc & Ors v Arip [2014] EWCA Civ 381, [2014] 1 CLC 451, Longmore LJ gave a salutary warning that there is a difference between being in a position of suspecting fraud and a position where one ought to have been aware of it: [24].
Over the years Nigeria certainly pursued settlement, but this was not the type of choice to a party’s advantage referred to in the Kalmneft authorities. In this case, if fraud was seriously on the cards, it would not have been to Nigeria’s advantage to continue to negotiate rather than to seek to upturn the award by investigating it. In my view Nigeria was seeking a reasonable settlement in light of the size of the damages the Tribunal had awarded. It certainly cannot be said that there was an informed choice not to investigate a fraud but to pursue a settlement. If Nigeria was not to pay the considerable amount awarded the only informed choice available was to seek a reasonable settlement which it could afford.
Especially telling in my view is that Nigeria’s international legal advisers, Curtis, underlined in July 2018 that if Nigeria wanted to advance fraud to challenge the awards it would need to have concrete evidence. There has been a problem of endemic corruption in Nigeria, as the Attorney General concedes, but I accept Mr Howard’s submission that that does not mean that every deal is potentially corrupt in the way, as I have concluded, this one prima facie is.
In this regard Henderson LJ’s words, albeit in the context of section 32 of the Limitation Act 1980, are apposite: the concept of reasonable diligence only makes sense if there is something to put the claimant on notice of the need to investigate whether there has been a fraud: Gresport Finance Limited v Carlo Battaglia [2018] EWCA Civ 540, [49]. In this case the trigger for a thorough fraud inquiry was absent.
At first blush the speed of the June 2018 EFCC investigation is somewhat troubling. But in terms of reasonable diligence it was not charged specifically with investigating fraud. The Attorney General’s letter to the EFCC of 28 June 2018, containing the President’s instructions, referred not to fraud but to a thorough investigation of the circumstances surrounding the GSPA and the subsequent events. In my view Mr Mill underplayed the work which was undertaken over the June 2018-August 2019 period. In particular there was the successful prosecution of P&ID and P&ID Nigeria on 19 September 2019, based on the groundwork undertaken during this fifteen-month period.
I accept that, compared to what happened after August 2019, it cannot be said that the investigation proceeded with the same sense of urgency. There is also Mr Malami’s letter, which became available after the hearing, and the investigation being carried out into the conduct of Mr Magu as acting head of the EFCC at the time. With respect I find it hard to read the letter as an attack on Mr Magu alone and not on the performance of the EFCC under his leadership. Mr Magu’s reference to the staggering volume of work done by the EFCC after June 2018 – if that is what his letter says – might be treated as special pleading.
In my view, however, this does not assist P&ID in its argument that reasonable diligence was lacking. There is certainly nothing to suggest that a deliberate decision was taken in the Takhar sense not to investigate fraud. Nor is there anything to suggest that there was a deliberate decision to proceed slowly. What occurred might have been the EFCC proceeding at its normal pace, in light of the resources allocated to it, the other inquiries it was conducting, and conditions in Nigeria.
By comparison the position after August 2019 might be exceptional and prompted by the serious position Nigeria faced in the light of Butcher J’s decision on P&ID’s enforcement application. At this point it is impossible to say. However, I cannot accept Mr Mill’s submission that there was no proper or diligent investigation. The basic point is that there was no specific information such that Nigeria ought to have become aware of the building blocks of the fraud now alleged.
From Butcher J’s judgment, 16 August 2019, to issue of current claim, 5 December 2019
In Mr Mill’s submission Nigeria had taken a deliberate decision following the Final Award not to investigate the alleged fraud, knowing that the deadline for challenging the award on that basis has long since passed, and that it only chose to do so after it had lost on the enforcement proceedings before Butcher J on 16 August 2019.
At this point, Mr Mill accepts, the Nigerian authorities moved swiftly. He adds, however, that apart from the appointment of a new legal team there was no explanation as to why, when P&ID and P&ID Nigeria had pleaded guilty to a number of counts on 19 September 2019, it still took until 5 December 2019 for the current claim to be issued.
To my mind the simple answer is that in our system allegations of fraud cannot be lightly made but require cogent evidence. As Elias LJ pointed out in Kazakhstan Kagazy plc & Ors v Arip [2014] EWCA Civ 381, [2014] 1 CLC 451, this is not simply a professional obligation of lawyers but because nobody should allege dishonesty lightly: [61].
Earlier the judgment identified how the picture began to emerge with the information from the banks and the interviews beginning in September 2019. The payments to Ms Taiga from Eastwise and ICIL were available in September, but they were the later payments in 2015 and 2019 so links had to be made both with P&ID and the GSPA. Mr Oguine mentioned the $100,000 from Mr Shasore in September, but he described it as a loan. Not until last December did the investigators learn of an equivalent $100,000 payment to Mrs Adelore. The Tita-Kuru letter came in late September, with the emerging picture of P&ID and how it won the GSPA, strengthened with Mr Tijani’s statement in November.
Overall, I accept Mr Howard’s submission that the Nigerian team needed to see the different building blocks to what they now allege as a massive fraud before proceeding with the current claims. In summary, the time from September 2019 until the proceedings taken in this court in December 2019 was modest in the circumstances and Nigeria’s behaviour reasonable.
Conclusion on delay and reasonableness
As alleged by Nigeria, the fraud is complex in character and continuing. Even on my preliminary examination it comprises a number of quite different strands. What occurred in this case was deliberately concealed. Especially with the international advisers it engaged, P&ID wore the cloak of legitimacy. In the circumstances which Nigeria has prima facie established, it acted reasonably in its investigations and in pursuing settlement.
Extension of time: the Kalmneft factors
Mr Mill’s case for P&ID was simple: to grant Nigeria an extension of time to challenge Tribunal awards issued three and five and a half years previously would be unprecedented. One of Mr Howard’s high-level points was that there seemed to be no example in the authorities where an extension of time was refused in circumstance where an appellant’s fraud challenge was prima facie made out, rather than being viewed with scepticism.
It seems to me that the best approach is to work through the Kalmneft factors as judges have done on many occasions previously. In doing so there is no need to reiterate in any detail the material in the previous sections of the judgment.
Factor (i): length of the delay
The length of the delay is unprecedented. The Liability Award was published approximately four and a half years, and the Final Award some two years and ten months, before the current proceedings were launched. Mr Howard did not seek to deny the very significant delay. His only point was that the reason for the delay was that P&ID successfully concealed its fraud during the arbitration, and for many years afterwards.
Factor (ii): “reasonableness”
Overall, for the reasons I have set out at length, I accept that there was nothing which Nigeria ought to have been aware of to act as a trigger causing a reasonable person, exercising reasonable diligence, to have discovered the alleged fraud.
Factor (iii): the respondent’s contribution to delay
Mr Mill’s argument was that there was no credible case that P&ID was responsible for Nigeria’s delay in issuing the current claims. I am afraid I cannot accept this. As explained above, I have held that Nigeria has established a strong prima facie case of fraud, which P&ID has prima facie covered up, thus contributing to the delay.
Factor (iv): prejudice to the respondent
Mr Mill’s contention was that an extension would cause irredeemable prejudice to P&ID because it was being kept out of its money for a further significant period. A fraud trial would not only take a considerable time, especially with appeals, it would be very expensive. There was also the further delay in the appeal on Butcher J’s enforcement decision, which would likely be postponed until after any fraud trial.
It seems to me that, where a party has a strong prima facie case of fraud, there can be no prejudice to the respondent in being subject to a full inquiry into the fraud at trial. As Mr Howard expressed it, an award that is liable to be set aside as having been procured by fraud is, in legal terms, worthless.
Factor (v): whether arbitration has continued during the period of delay
This factor is not applicable.
Factor (vi): strength of the application
As we have seen, in discussing this factor in the Nagusina Navier case [2002] EWCA Civ 1147, [2003] 2 CLC, Mance LJ said it was material that the case was not one where the appellants’ challenge was so strong that it would obviously be a hardship for them not to be able to pursue it: [41]. Similarly, in Terna [2012] EWHC 3283 (Comm), [2013] 1 Lloyd's Rep 86, Popplewell J said that where a court could see on the material that the challenge involved an apparently strong case that would assist the application: [31]. (I note that in L Brown & Sons v Crosby Homes [2008] EWHC 817
(TCC), Akenhead J said “positively assist”, although this may amount to the same thing: [32(c)]).
For the reasons already given, Nigeria has to my mind a strong prima facie case in fraud in its serious irregularity challenge. On closer investigation this is not the type of case Butcher J rightly warned about in his judgment ordering the present hearing, where a party who has been unsuccessful in the arbitration alleges fraud in relation to the procurement of the underlying contract or in relation to the conduct of the arbitration, when that was not properly investigated at the time of the arbitration: The Federal Republic of Nigeria v Process & Industrial Developments Limited [2020] EWHC 129 (Comm), [31].
Factor (vii): fairness “in the broadest sense”
Mr Mill submitted that this factor had no weight given the public policy goals of finality, non-intervention and adherence to time limits in the court’s approach to arbitration challenges. We saw that Mance LJ referred to these factors in Nagusina Navier case [2002] EWCA Civ 1147, [2003] 2 CLC, [42]. There are other authorities to similar effect.
As mentioned earlier, it should not be forgotten that as well as these principles section 1 of the 1996 Act refers as to the fair resolution of disputes as a general principle, and to party autonomy as being subject only to necessary public interest safeguards. While judicial views differed as to the appropriate level in Westacre Investments Inc v Jugoimport SDPR Holding Co Ltd [2000] QB 288, all agreed that commercial corruption attracted strong judicial disapproval: at 315, 317; see also [1999] QB 740, 773.”. I also note that Cockerill J recently opined that there is no rule of law which automatically prioritises the finality of arbitral awards over the public policy of refusing to endorse illegal conduct: Alexander Brothers Limited (Hong Kong SAR) v
Alstom Transport SA Alstom Network UK Limited [2020] EWHC 1584 (Comm), [148].
With that as background I find persuasive Mr Howard’s submission that the fairness factor does have an impact in challenges where there is strong prima facie evidence of fraud, certainly of the through-going character alleged in this case. Not only is the integrity of the arbitration system threatened, but that of the court as well, since to enforce an award in such circumstances would implicate it in the fraudulent scheme.
Conclusion on the Kalmneft factors
The delay in this case is extraordinary and weighs heavily on the side of the balance against an extension. In my view, however, other factors bring it down in favour of an extension.
As I have explained, the delay is not in my view the result of a deliberate decision made because of some perceived advantage, and in all the circumstances Nigeria has acted reasonably. Given the strong prima facie case of fraud which I have concluded Nigeria has established, the position is along the lines of that identified in Terna, where Popplewell J identified the substantial injustice an applicant would suffer in respect of the underlying dispute if deprived of the opportunity of making a challenge should an extension of time be refused: Terna Bahrain Holding Company WLL v Bin Kamil Al Shamsi [2012] EWHC 3283 (Comm), [2013] 1 Lloyd's Rep 86, [33].
For the reasons I have given, P&ID has contributed to the delay, and it will not by reason of the delay suffer irremediable prejudice in addition to the mere loss of time if the application is permitted to proceed. Although not a primary factor, fairness in the broadest sense favours an extension in this case.
Conclusion
For the reasons given, I grant Nigeria’s applications for an extension of time and relief from sanctions.