Skip to Main Content

Find Case LawBeta

Judgments and decisions from 2001 onwards

Euroil Ltd v Cameroon Offshore Petroleum Sarl

[2014] EWHC 215 (Comm)

Case No: 2014 FOLIO 6
Neutral Citation Number: [2014] EWHC 215 (Comm)
IN THE HIGH COURT OF JUSTICE
QUEEN'S BENCH DIVISION
COMMERCIAL COURT

Royal Courts of Justice

Strand, London, WC2A 2LL

Date: 07/02/2014

Before :

THE HON. MR JUSTICE MALES

Between :

EUROIL LTD

Claimant/ Applicant

- and -

CAMEROON OFFSHORE PETROLEUM SARL

Defendant/ Respondent

Mr M. Cook (instructed by Shepherd and Wedderburn LLP) for the Applicant/Claimant

Mr Vernon Flynn QC and Ms Philippa Hopkins (instructed by Clyde & Co. LLP) for the Respondent/Defendant

Hearing dates: 14 January 2014

Judgment

Mr Justice Males :

1.

Following delivery of my extempore judgment ([2014] EWHC 52 (Comm)) in which I set aside the injunction originally granted on 6 January 2014 there was insufficient time to deal fully with the question of costs. As I was due to be sitting out of London for the next six weeks I ordered that the claimant Euroil should pay the defendant Camop’s costs of the application to discharge the injunction, that such costs should be summarily assessed on the standard basis, and that the parties should make written submissions as to quantum, with Euroil making such points as it wished to on the schedule of costs which had been served by Camop, followed by a response from Camop, after which I would assess the costs to be paid.

2.

At that stage Camop had served a schedule of costs for the application totalling £236,651, which compared with a schedule served by Euroil totalling £58,513. As directed, Euroil served its written submissions, but instead of confining these to the quantum of costs for summary assessment, it reiterated its submission that the matter was more suitable for detailed assessment, principally because it was apparent from the Camop schedule that some of the costs claimed related to work which was part of the arbitration process, that other costs represented costs of attending the meetings in Cameroon which could not be regarded as costs of the application to discharge, and that while it was therefore clear that some of the costs claimed would have to be disallowed, there was insufficient information in the schedule to enable the assessment of which costs were attributable to the application to discharge to be carried out with reasonable accuracy. There appeared at first sight to be force in these points. Having done that, Euroil made a series of points as to why it said that the figures claimed by Camop were too high.

3.

In response, Camop has rightly acknowledged the validity of some of the points made by Euroil, explaining that (understandably) its schedule had been prepared in considerable haste, and putting forward a revised schedule showing a total costs figure of £213,932. This led, reasonably enough, to an indication by Euroil’s solicitors that they would wish to have the opportunity to make submissions on the revised schedule before I carried out the assessment which had been envisaged.

4.

It was my intention at the hearing, and I ordered, that Camop’s costs should be summarily assessed, that being in general the appropriate course for a hearing which lasted for a long half day. However, the exchanges to which I have referred and the understandable changes in the costs now sought by Camop have shown that a summary assessment procedure would now be somewhat more protracted than then envisaged. I could hardly refuse Euroil the opportunity to comment on the new schedule which is now put forward by Camop, and it is likely that Camop would then wish to answer whatever criticisms of its new schedule might be made. The benefit of a summary assessment to the parties is precisely that the assessment should be summary, thereby saving costs, even if this results in a more approximate figure than would be obtained on a detailed assessment. However, the current position, with what may become lengthy exchanges of correspondence, seems to me to represent an unsatisfactory half way house between the two procedures.

5.

I am persuaded, therefore, that in this case where the assessment is not altogether straightforward and a substantial costs sum is in issue, the right course is to order that there should after all be a detailed assessment, together with a payment on account in the sum of £120,000 in accordance with Camop’s alternative submission. I am satisfied that this is the minimum figure which Camop will recover and is a reasonable figure to award in accordance with CPR 44.2 (8).

6.

I should also make the following observations for the assistance of the parties and, if necessary, the costs judge who will carry out the detailed assessment:

(1)

This was a significant and substantial application requiring extensive work as a matter of urgency under considerable time pressure.

(2)

It was reasonable and necessary for Camop to prepare the detailed evidence which it served for the application.

(3)

The allegations of contempt made by Euroil will have added to the care and attention required in the preparation of Camop’s evidence, and it was reasonable and necessary for Camop to be prepared to answer these allegations at the hearing even though no application to commit had been issued. The contempt allegations mean that it was also reasonable for there to be a higher degree of partner involvement and oversight than might otherwise have been the case.

(4)

The cost of Mr Wachtel’s time in attending the meetings in Cameroon cannot be claimed as part of the costs of the application as he was due to attend those meetings in any event. The reasonable cost of preparing his witness statement can.

(5)

It was reasonable and necessary for Camop to instruct Clyde & Co, including a partner and assistant from the litigation department.

(6)

It was reasonable and necessary for Camop to instruct leading and junior counsel, though I am unable to comment on the reasonableness of their fees without knowing more about the number of hours worked which those fees represent.

(7)

It was reasonable for Mr Wachtel to be present at the hearing in addition to members of Clyde & Co’s litigation department.

7.

Finally, Camop seeks an order for an inquiry as to damages on the cross undertaking given by Euroil’s parent company Bowleven Plc. As shown by the recent judgment of Blair J in Malhotra v Malhotra [2014] EWHC 113 (Comm), the question whether to order such an inquiry is not always straightforward. If such an order is to be sought, there should be an application supported by evidence and, in any event, such an application would be better made in what is still a developing situation once it is possible for Camop to give a realistic assessment of what loss, if any, it claims to have suffered as a result of the order.

Euroil Ltd v Cameroon Offshore Petroleum Sarl

[2014] EWHC 215 (Comm)

Download options

Download this judgment as a PDF (120.5 KB)

The original format of the judgment as handed down by the court, for printing and downloading.

Download this judgment as XML

The judgment in machine-readable LegalDocML format for developers, data scientists and researchers.