Date: 8 October 2026
Before: His Honour Judge Richard Carter sitting as a Judge of the High Court
Between:
(1) AIRX JET SUPPORT LIMITED (2) AIRX CHARTER LIMITED | Claimants |
- and – | |
(1) LONDON JET CENTRE (STANSTEAD) LIMITED (also known as LONDON JET CENTRE (STANSTED) LIMITED) (2) DIAMOND HANGAR LIMITED | Defendants |
Richard Fowler (instructed byPannone Corporate LLP)for the Claimants
Nicholas Grundy KC and Christopher Stead (instructed byRobinson Ravani & Co Ltd)for the Defendants
Hearing dates: 23 July 2026
Approved Judgment
I direct that pursuant to CPR PD 39A para 6.1 no official shorthand note shall be taken of this Judgment and that copies of this version as handed down may be treated as authentic.
.............................
His Honour Judge Richard Carter:
Introduction
By an application dated 15 April 2025, the Claimants, AirX Jet Support Limited (“Jet Support”) and AirX Charter Limited (“Charter”) sought interim mandatory injunctive relief in relation to a substantial aircraft hangar at Stansted Airport (“the Hangar”) occupied by the Claimants. The Claimants operate their business as a private jet airline and charter provider from the Hangar. They sought an order, as set out in the Application Notice, that the Defendants, London Jet Centre (Stanstead) Limited (“LJC”) and Diamond Hangar Limited (“DH”), should
repair the roof of the Hangar so as to render it watertight and safe and
supply heating to the Hangar. The Defendants opposed the Application.
The Application came on before Mr Andrew de Mestre KC sitting as a Deputy High Court Judge on 19 September 2025. On 14 October 2025, the Deputy Judge handed down judgment by email. A copy of the Judgment is in the Application Bundle at 1420.
By an Order dated 8 December 2025, the Deputy Judge made an interim order against the Defendants limited to the application to supply heating. The Defendants were required to “…use their best endeavours to carry out or procure the carrying out of” the “Gas Heating Obligation” defined in §4.1 of the Order. In respect of the Application for a mandatory injunction to repair the Hangar Roof (“the Hangar Roof Application”) the Deputy Judge gave directions for the appointment of expert roofing surveyors, for expert reports and for a joint statement. He relisted the Hangar Roof Application on the first available date after 13 February 2026.
This is the hearing of the adjourned Hangar Roof Application. A draft Order (updated to reflect the position as of July 2026) sought by the Claimants is at 21 in the Bundle and seeks the following:
By 4 p.m. on [the date 21 days from the date of this Order] the Respondents shall carry out or procure the carrying out of temporary repairs to the Hangar roof (“the Temporary Repairs”) so as to render the Hangar roof watertight, as follows:
The Respondents shall apply a new liquid-based roofing system over the existing roof surface, including previously repaired and replaced areas, in accordance with paragraphs 6, 2) of the Hopkinson Report.
The Respondents shall carry out compatibility and adhesion tests of all the roof finishes now in place and if the area beyond the demise of the Hangar is not to be treated, the new coating will be required to be extended approximately 1m beyond the boundary of the Hangar’s demise, in accordance with paragraphs 6, 2) of the Hopkinson Report.
[alternatively:
The Respondents shall carry out or procure the carrying out of such Temporary Repairs as will render the Hangar roof watertight and safe until the handing down of judgment at the trial of this action, which trial is to be listed for hearing in a window between [date] and [date].]
The Background
The Claimants are the occupiers of the East half of the Diamond Hangar at Stansted Airport in Essex (“the Hangar”). The Defendants are in common ownership, sharing management and staff.
The Claimants claim to be tenants (or alternatively licensees) of the Hangar from the Defendants (it is unclear which of the parties are the tenant/licensee/landlord). They do however pay rent/licence fees and service charges for their occupation as well as fees for contractual services provided by the Defendants.
The Claimants claim that the Defendants’ obligations as landlords/licensors to the Claimants include:
Keeping the Hangar roof in repair; and
Supplying heating at the Hangar – the costs of the gas heating are to be paid out of the service charges.
The Defendants do not accept the scope of these obligations but accept that they owe some duties to the Claimant. At §36 of the defence the Defendants plead:
“36.2. However, it is admitted that the licence by which the Defendants aver Jet Support uses and occupies the east half of the Hangar as licensee of DH contains implied terms that the premises will be reasonably fit for the purpose for which the licence is agreed, and that such a term in principle extends to the repair of the roof and the provision of adequate heating.
36.3. Alternatively, it is admitted that the tenancy at will as averred would contain a similar implied term.”
In his Judgment, the Deputy Judge summarised the issue on the repairing obligation as follows:
“For their part, the Defendants say that neither LJC nor Charter has any interest in the Hangar, and that Jet Support occupies the east half of the Hangar as a licensee of DH from month to month or as a tenant at will. They also deny that they owe the repairing and heating obligations relied on by the Claimants but accept that it would be an implied term of the licence or tenancy at will on which they rely that the east half of the Hangar will be reasonably fit for purpose and that such a term “in principle extends to the repair of the roof and the provision of adequate heating” (Defence, ¶36.2-36.3). In his oral submissions, Mr Grundy KC for the Defendants, submitted that this implied term could not extend as far as ensuring that the roof did not leak.”
The Claimants allege that the Defendants are in breach of those obligations in that they have:
Failed adequately to maintain or repair the roof, which suffers from substantial and serious leaks in wet weather that frequently cause water ingress onto the Hangar floor and onto the Claimants’ aircraft, equipment and offices; and
Since 2024 failed to switch on the gas heating, instead supplying a small number of free-standing heaters which the Claimants contend are inadequate. The Claimants complain that it is difficult for their employees to work in cold weather, and the lack of adequate heating increases disruption caused by wet weather.
As a result of those breaches, the Claimants allege that they have suffered loss. The breaches have caused restrictions to the work that can be carried out in the Hangar. These issues (they contend) also present a serious risk of physical harm to the Claimants’ employees, and to third parties. In addition, they contend that, being subject to regulation by the European Air Safety Agency (“EASA”) and the UK Civil Aviation Authority (“CAA”), the above issues have put their regulatory approval with both bodies at risk, and that if the issues are not resolved, they may be forced to cease operation at their next CAA inspection in November 2026.
This Application therefore sought the following relief:
A mandatory injunction requiring the Defendants to repair the roof and to restore the gas heating.
In the alternative, an adjournment to allow their proposed expert Mr Greenwood to inspect the roof.
Alternatively, a declaration that the Claimants have a licence to access the roof to carry out their own repairs.
Further or alternatively, the appointment of a receiver to repair the roof and restore the heating.
As noted above, the Application came on before Mr Andrew de Mestre KC who granted an interim mandatory injunction requiring the Defendants to restore the gas heating on “best endeavours” terms and directed that new experts for both parties inspect the roof and report as to its state of repair. It is the Claimant’s case that the heating has still not been restored, and they intend (I am told) to issue an application to enforce that part of the Deputy Judge’s order. However, that is not an issue before me.
On the Hangar Roof Application, the Deputy Judge concluded that:
The Claimants had established a “serious issue to be tried”.
That damages would not be an adequate remedy.
He was not (yet) satisfied that the balance of convenience favoured the grant of an interim mandatory injunctions in the terms sought by the Claimants:
“The principal reason for this is that, although there have been significant issues with the roof both historically and in the last year, I am not satisfied that I have a sufficiently clear and up-to-date understanding of the state of the roof to be satisfied that the balance falls in favour of the Claimants”
He therefore made the order for experts to inspect the roof.
The Claimants say that the sole live issue before the Court is the “balance of convenience” test. In considering that test they invite the Court to consider the following evidence:
Mr Hopkinson’s report on behalf of the Claimants dated 2 February 2026 (“the Claimants’ Report”)
Mr Lehmann’s report on behalf of the Defendants dated 10 March 2026 (“the Defendants’ Report”)
Mr Sawyer’s report on behalf of the Defendants (disavowed) dated 3 February 2026 (“The Sawyer Report”)
The Joint report of Mr Hopkinson and Mr Lehmann dated 8 July 2026 (“the Joint Report”)
The 5th and 6th Statements of Mr Matthews on behalf of the DefendantsClaimants
.
The Defendants assert that the reason for the adjournment of the Claimants’ repair application was that their evidence was inadequate – i.e. that there was no reliable evidence that the roof was not watertight, nor indeed that the Defendants had any contractual duty to the Claimants to maintain the roof in a watertight condition. Mr Grundy pointed to the basis of the further expert evidence – that the report shall address the following matters:
Whether or not the Hangar Roof is currently (i) weatherproof, and (ii) watertight, and
If the Hangar Roof is currently (i) not weatherproof and/or (ii) not watertight, what temporary repairs could be carried out to make it weatherproof and/or watertight until the trial of this claim (which for the purposes of this Order the Experts shall assume will take place in the next 12-18 months) “the Temporary Repairs”.
How long it would take to carry out the Temporary Repairs, how much they would cost, and how long they could reasonably be expected to be effective in keeping the Hangar Roof weatherproof and/or watertight.
Lay Evidence
I do not propose to set out in detail the evidence filed in support of and in opposition to the Application, both by lay (including professional) witnesses and by the experts. The Deputy Judge included in his judgment a summary from §10-14 which I adopt.
However, the Claimants have filed further evidence of water ingress. In Matthews 5, he sets out incidents from 17 September 2025 through to 3 June 2026 where there has been water ingress. Photographs and video have been supplied showing water pooling/leaks. The evidence includes damage to aircraft parts, water pooling and debris falling from the roof. However, as I note below there is no evidence from the experts to show the causes of these incidents, nor have the experts been asked to comment on the photographs/videos.
The Defendants have challenged this evidence – see Covaci 3 – and have filed photographic and video evidence which they contend shows no evidence of water ingress, save where there is a potential separate explanation, and no evidence that the roof is not watertight/weatherproof. Again, that is not evidence that the experts have considered or commented on.
I am satisfied that there are occasions when there has been water ingress into the Hangar through the roof, especially at times of exceptionally poor weather (e.g. Storm Chandra and the storms in June 2026). The videos supplied by the Claimants clearly show water leaking. I accept that the Defendants’ roofing contractor Dean Simmonds appears to have inspected the roof (after the June incident) and concluded that there was no leak. However, that is not evidence which has been considered by the experts.
The Defendants have also suggested that water has been entering the Hangar through the hangar doors. The Claimants’ expert had noted at §4.12 that:
“There was some evidence of standing water to the hangar floor (adjacent to the hangar doors in particular) but it is not possible to be certain if this has been caused by trafficking of the floor by aircraft or other vehicles, wind-blown rain when the hangar doors are open or rainwater penetration.”
In response to questions from the Defendants’ Solicitors, he responded that it was not possible to determine with certainty the source of the standing water, and that he was unable to conclude on the balance of probabilities the source of water in the Hangar.
Unfortunately, it is not possible on the evidence before me to determine the extent to which incidents of water ingress are the result of the roof not being watertight/weatherproof, and which may be caused by other factors. In any event, as noted below, the Expert reports do not assist me on this.
The Claimants also provided (very late) evidence from Mr Matthews (Matthews 6) on 22 July 2026. He provided a schedule of estimated losses “…associated with the Hangar roof, lack of heating and low temperatures”. Surprisingly as this hearing deals only with the Hangar Roof Application, no attempt has been made to separate out the different causes of the claimed losses.
Mr Grundy noted that the shutdowns which form most of the losses claim relate to temperature. The damage to the Claimants’ property, he suggested, is limited to (approx.) £10,000. Mr Grundy also pointed to issues about the extent of the relevant demise as some of the incidents relate to the office area – which falls outside the Hangar Roof.
The (new) Expert Evidence
All three Experts found that:
There was no evidence of water ingress through the roof at the time of inspection.
The roof had exceeded or was approaching the end of its anticipated lifespan.
The Defendants’ expert concluded that the roof in its current condition would withstand heavy weather. The Claimants’ expert did not answer that question rather stating as follows:
“Whether or not the hangar roof is currently (i) weatherproof and (ii) watertight
Having regard to the evidence of previous rainwater penetration, failures and detachment of the membrane/insulation and the corroding of the fixings and, based upon a single visual inspection on a dry day, it is my opinion that it is not possible to state with any certainty that the hangar roof is or is not presently weatherproof or watertight.
It is however my opinion that the roof coverings have exceeded their anticipated life, are now beyond economic repair and that if they are presently weatherproof and watertight, further rainwater penetration and failures will most probably continue to occur in the future on a regular basis until complete replacement is carried out.”
The experts provided very different conclusions as to the temporary works required to secure the roof:
The Claimants’ Expert proposes works costing between £512,000 and £1.2M. He states that the work he proposed “… may prove effective for 12-18 months” although he had not identified any specific disrepair that requires remediation.
The Defendants’ Expert proposes works costing £128,000. He states that he would expect the works to be weatherproof and watertight for 3 – 4 years.
The Joint Report dated 8 July 2026 records the following areas of agreement:
that most of the roof covering remained the originally mechanically fixed single ply membrane system installed when the building was constructed circa 1989.
that the system is now therefore circa 37 years old and has exceeded its life span of 25-35 years.
that the roof is unlikely to comply with the current regulations of BS 6229 re roof and gutter falls or the requirements of BS 1991 re mechanical fixings.
that the thermal performance of the existing 50mm mineral wool roof insulation does not comply with current recommendations of Approved Document L1 to the Building Regulations, and that Reg 23(2) requires that when replacing > 50% of the thermal elements surface area, the whole of the thermal element must be replaced.
that a variety of materials have been used to carry out previous repairs and that repairs after storm damage had included replacement of the original Rockwool insulation with new PIR insulation.
There was a difference in compressive strength between the original and replacement insulation allowing differentiation of the original and replacement areas.
That the most appropriate form or temporary repair would be to apply a new liquid-based roofing system to the existing roof surface.
The following were not agreed:
The Defendants’ expert’s proposal to exclude the areas previously replaced/repaired.
His proposal to provide new mechanical fixings to the existing membrane and insulation.
As to the practicality and implications of retrofitting pressure plates (mechanical fixings) to the existing roof membrane, the Claimants’ expert agreed that if new fixings are not provided, the risk of detachment of the membrane and insulation in storm conditions will remain, but he noted that the provision of new fixings would require thousands of penetrations to the existing roof coverings which are in poor condition.
The Defendants’ expert noted he had not yet consulted the manufacturers of the membrane/mechanical fixings as to the practicality of retrofitting the fixings but agreed that it was unlikely that they would approve such a plan. As such no guarantee was likely to be forthcoming.
Mr Fowler noted that all three experts consider that the roof is beyond its effective life and in need of replacement and that there is a serious and growing risk that the roof will fail catastrophically:
Mr Hopkinson stated that “It is also anticipated that corrosion and failure of fixings will be ongoing and progressive” and that “…the requirement to carry out such [monthly] inspections suggests that further defects are expected to become apparent on a regular basis particularly following high winds or storm conditions”.
Mr Lehman says “As the roof consists of two large installations, the old / original and the new of approximately 1,200m2 , I do not believe that the old / original roof would withstand another strong storm or hurricane due to the uncertainty of the old fixings are adequate to withstand heavy storms. The new roof installation does appear to be sufficiently secure to withstand heavy weather.”
As neither expert has considered the additional photographic and video evidence, their conclusions on whether it is weatherproof/watertight are based on their inspections. Mr Lehmann stated at §6(1)(ii):
“It is my opinion that the roof is currently watertight as there was no evidence to suggest otherwise. The old / original roof is however reaching the end of its lifespan so I would not be surprised if it would fail in the foreseeable future although this is all subject to weather conditions, which I cannot predict.”
Mr Hopkinson as noted above stated that “it is my opinion that it is not possible to state with any certainty that the hangar roof is or is not presently weatherproof or watertight.”
In his joint report with Mr Sawyer they stated:
“It was agreed that based on the visual inspection undertaken during our joint inspection of the existing waterproofing membrane, no further evidence of splits, tears, or other defects was observed. This suggests that on the day of the joint inspection, the roof was performing in a watertight manner. However, it is not possible to confirm this with absolute certainty.
It was also agreed that the evidence and reports of previous rainwater penetration provided by others and the fact that only a single inspection was carried out on a dry day should also be taken into account when considering the results of the inspection.”
The purpose of the instruction of the experts was to determine whether the roof was “weatherproof and watertight”, and if it was not then to identify what temporary works could be effected. Neither expert has confirmed that the roof is not watertight/weatherproof despite the factual evidence provided by the Claimants since the adjournment.
Legal Test
In his judgment at §23-27 the Deputy Judge set out the appropriate test for the granting of interim injunctions. The legal principles to be applied are agreed to be those contained in American Cyanamid – ie the applicant must establish that there is a serious issue to be tried, that damages would not be an adequate remedy for the applicant if the injunction was refused, and that the balance of convenience favours the granting of an injunction.
The Deputy Judge then highlighted the following issue between the parties:
The principal difference between the parties concerned the relevance of the merits of the underlying proceedings and, in particular, whether or not the Court should not grant an injunction unless there is a “high degree of assurance” that, at trial, the applicant will establish the right on which it relies for the interim relief sought. Between them, the parties referred to a number of authorities in which that issue has been considered: Films Rover International Ltd v Cannon Film Sales Ltd [1987] 1 WLR 670, Nottingham Building Society v Eurodynamics Systems [1993] FSR 468, National Commercial Bank of Jamaica Ltd v Olint Corp Ltd (Practice Note) [2009 1 WLR 1405 (PC), and O’Brien v TTT Moneycorp Ltd [2019] EWHC 1491 (Comm).
It seems to me that the principle to be derived from these authorities is that, while it is not necessary for the court to have a “high degree of assurance” in every case, the Court will generally wish to consider the merits of the applicant’s case as part of assessing where the balance of convenience lies. Given that the underlying principle is that the Court should take whichever course appears to carry the lower risk of injustice if it should turn out at trial to have been “wrong”, the greater the degree of assurance which the Court has in the applicant’s case then the less the risk of injustice will be if a mandatory order is granted. Thus a high degree of assurance will often be a relevant factor in favour of the grant of a mandatory injunction. Equally, it will generally only be in cases where withholding the injunction would carry a significantly greater risk of injustice than granting it that the Court will proceed without the relevant high degree of assurance.
In his Skeleton, Mr Grundy referred to the summary of relevant principles set out by Christopher Hancock QC sitting as a Judge of the High Court in O’Brien and another v TTT Moneycorp Ltd [2019] EWHC 1491 (Comm) at §67:
A mandatory injunction is less likely to be granted on an interim basis. This is because, where other factors appear to be evenly balanced, the Court "should take whatever course seems likely to cause the least irremediable prejudice to one party or the other": National Commercial Bank Jamaica Ltd v Olint Corp Ltd (Practice Note) [2009] 1 WLR 1405 (PC). A mandatory injunction requiring a party to take some positive step at an interlocutory stage will usually carry a greater risk of injustice if it turns out to have been wrongly made. It is therefore legitimate in such cases to require a "high degree of assurance" that the interim relief would ultimately be granted at trial: Shepherd Homes Ltd v Sandham [1971] Ch 340 at 351 (Megarry J).
Furthermore, where the grant of interim relief will have the practical effect of giving the applicant the final relief that it is seeking in the case, the Court will be more reluctant to grant such relief: Films Rover Ltd v Cannon Film Sales Ltd [1987] 1 WLR 670 at 680.
Mr Fowler submitted that the need for a “high degree of assurance” was qualified by two cases:
In National Commercial Bank of Jamaica Ltd v Olint Corp Ltd (Practice Note) [2009] UKPC 16, [2009] 1 WLR 1405, the Privy Council identified the real test as being to seek to predict whether granting or withholding the interim injunction is more or less likely to cause irremediable prejudice, and to what extent, if it turns out at trial to have been wrongly granted / withheld; and
In Films Rover International Ltd v Cannon Film Sales Ltd [1987] 1 WLR 670, it was said that, if the Court considers that withholding a mandatory interim injunction carries a greater risk of injustice than granting it, it may grant it, even if it does not feel a “high degree of assurance” that the claimant will establish their rights at trial.
Further, in relation to breaches by a landlord of repairing obligations in a lease, there is authority that the Court may make an interim mandatory order to carry out repairs – Peninsula Maritime Ltd v Padseal Ltd [1981] 2 EGLR 43 and Parker v Camden LBC [1986] Ch 162 (CA). In Parker it was described as an “exceptional” remedy but was granted because the landlord’s breaches involved a risk to individual’s physical wellbeing, not merely a risk of loss and damage. It is the Claimants’ case that there is such a risk of physical injury in this case because of leakage of water onto the floor. Further, Mr Fowler pointed to the risk of catastrophic roof failure.
Analysis
Serious Issue in Dispute
Mr Fowler submitted that there was clearly a serious issue to be tried. Although there are disputes between the parties as to the status of the Claimants’ occupation, and the extent of the repairing obligations to which the Defendants are subject, the Hangar roof is clearly leaking and is causing, and will cause, loss and damage to the Claimants.
The Deputy Judge had this to say about the question of “a serious issue to be tried”:
“38. I am satisfied that there is a serious issue to be tried on this question. I have already set out the relevant terms of the Defence at paragraph 7 above which accepts that, even on the Defendants’ own case, the implied term to Jet Support’s licence extends in principle to the repair of the roof. Likewise, the Defendants’ skeleton argument for the hearing did not say, in terms, that there was not a serious issue to be tried. It simply said that “It is far from certain that Rs have any duty…to maintain the Roof”.
He went on to note that the Defendants’ case is that there several different ways in which the Claimants put their case, and therefore there is material uncertainty about the standard of any duty owed. However, he took the view that issues about the relevant contracting party and the relevant routes to an enforceable duty to repair were not something that affected whether there was a serious issue. Looking at the pleaded cases in the round, the existence of a repairing obligation was such an issue.
I fully concur with the Deputy Judge’s conclusion. The occupation of the Claimants (and/or each of them) of the Hangar, together with the substantial payments made by the Claimants for that occupation, taken with a history of repairs to the roof, satisfy me that this is an issue which will need to be determined by the Court at Trial. I shall return to the issue of whether there is a duty to keep the roof watertight and weatherproof below.
Adequate Remedy
The second limb is whether damages would be an adequate remedy for the Claimants if the injunction is not granted and for the Defendants if it is granted. The Deputy Judge stated as follows:
“It seems to me that, in principle, this issue supports the Claimants. If a mandatory order were to be made, the Claimants’ case is that the temporary repairs which it seeks could be carried out relatively cheaply and quickly. If the Claimants were then to lose at trial, the Defendants would be protected against the costs they would have incurred by the cross-undertaking offered by the Claimants, the adequacy of which was not disputed. In the meantime, the proposed repairs to the roof would benefit not just the Claimants but also the Defendants who are occupying the other half of the Hangar.”
Of course, the Deputy Judge was reliant on the evidence of Mr Greenwood who had suggested that the costs of repairs would be in the region of £18,250, rather than the current estimates.
In contrast, he pointed to the potential losses to the Claimants as well as the risks to their personnel “…caused by the roof failures and the presence of significant amounts of water in their working environment. It will also be difficult to quantify the loss caused by that water through, for example, the loss of productivity.”
The additional evidence of Mr Matthews would suggest that (at best) the losses caused to the Claimants would be in the region of £250k for a 2-year period. Even the lower figure for the temporary works suggested by the Claimants’ expert would be twice that figure, and the upper figure would be approximately 5 times. However, if the loss attributable to the water ingress was in fact around £10,000 then the cost to the Defendants would far exceed any loss to the Claimants.
As for the issues with the EASA and CAA accreditation, the report at 925 relates solely to temperature issues:
“The organisation was unable to demonstrate compliance with point (c) 1, of 145.A.25, with regard to the temperature being maintained within the working environment, such that personnel can carry out required tasks without undue discomfort.
Evidenced by: AirX Jet Support Filename ‘logTag_D0C1002956KT_8_260109_1908_ALM.pdf ‘did not demonstrate an appropriate working environment was present, such that personnel did not suffer undue discomfort.
The AirX Jet Support, Cold Weather Operations Policy (Work Instruction: JSWI 037, Issue: 3, Date: 06 January 2026).
Limitation: No base maintenance activities to be carried out at the facility on UK (G Registered) aircraft until such time that it can be demonstrated to the regulator (UK CAA) that the temperature within the facility can be maintained such that personnel can carry out required tasks without undue discomfort and their effectiveness is not impaired”
The Defendants’ expert suggests repair works would cost some £128,000 and would ensure that the roof remained watertight/weatherproof for 3-4 years (ie until beyond trial). However, those costings must be considered in the light of the limitations highlighted in the joint report that Mr Lehmann had not consulted the manufacturers regarding the practicality of retrofitting the fixings (and that no formal approval would be forthcoming).
Clearly the basis on which the Deputy Judge made his finding that the adequacy of damages lay in favour of the Claimants no longer persists. He was reliant on an unrealistic estimate of the costs of compliance with the mandatory order, and did not have evidence of losses which the Claimants might suffer.
I am not satisfied that the evidence of the Claimants establishes that the effect of sporadic water ingress into the Hangar would (1) cause issues with their regulator, (2) cause substantial losses, or (3) put their staff at risk of personal injury. Where there has been water ingress, it appears to have been dealt with by the Claimants in the usual way – such as cordoning off areas and cleaning. There is no good evidence therefore that the on-going losses to the Claimants could not be an adequate remedy if successful at Trial although I accept that assessing that loss might be difficult.
Similarly, although the cost to the Defendants would be substantial, there is no reason to believe that the cross undertaking in damages would not be an adequate remedy for the Defendants if ultimately the repair works required by the order were wrongly granted.
Balance of Convenience
As noted above the Defendants referred to O’Brien v TTT Moneycorp Ltd at §67(5). In that case the Applicants submitted that:
“(5) A mandatory injunction is less likely to be granted on an interim basis. This is because, where other factors appear to be evenly balanced, the Court " should take whatever course seems likely to cause the least irremediable prejudice to one party or the other ": National Commercial Bank Jamaica Ltd v Olint Corp Ltd (Practice Note) [2009] 1 WLR 1405 (PC) .
A mandatory injunction requiring a party to take some positive step at an interlocutory stage will usually carry a greater risk of injustice if it turns out to have been wrongly made. It is therefore legitimate in such cases to require a " high degree of assurance" that the interim relief would ultimately be granted at trial: Shepherd Homes Ltd v Sandham [1971] Ch 340 at 351 (Megarry J).”
The Respondent in O’Brien referred to National Commercial Bank Jamaica Ltd v Olint Corpn Ltd where the Privy Council stated that:
“17. In practice, however, it is often hard to tell whether either damages or the cross-undertaking will be an adequate remedy and the court has to engage in trying to predict whether granting or withholding an injunction is more or less likely to cause irremediable prejudice (and to what extent) if it turns out that the injunction should not have been granted or withheld, as the case may be. The basic principle is that the court should take whichever course seems likely to cause the least irremediable prejudice to one party or the other.”
19…. What is true is that the features which ordinarily justify describing an injunction as mandatory are often more likely to cause irremediable prejudice than in cases in which a defendant is merely prevented from taking or continuing with some course of action: see Films Rover International Ltd v Cannon Film Sales Ltd [1987] 1 WLR 670, 680. But this is no more than a generalisation. What is required in each case is to examine what on the particular facts of the case the consequences of granting or withholding of the injunction is likely to be. If it appears that the injunction is likely to cause irremediable prejudice to the defendant, a court may be reluctant to grant it unless satisfied that the chances that it will turn out to have been wrongly granted are low; that is to say, that the court will feel, as Megarry J said in Shepherd Homes Ltd v Sandham [1971] Ch 340, 351, “a high degree of assurance that at the trial it will appear that the injunction was rightly granted”.
20 For these reasons, arguments over whether the injunction should be classified as prohibitive or mandatory are barren: see Films Rover [1987] 1 WLR 670, 680. What matters is what the practical consequences of the actual injunction are likely to be. It seems to me that both Jones J and the Court of Appeal proceeded by first deciding how the injunction should be classified and then applying a rule that if it was mandatory, a “high degree of assurance” was required, while if it was prohibitory, all that was needed was a “serious issue to be tried”. Jones J thought it was mandatory and refused the injunction while the Court of Appeal thought it was prohibitory and granted it.
21 Their Lordships consider that this type of box-ticking approach does not do justice to the complexity of a decision as to whether or not to grant an interlocutory injunction.”
The key issue is not whether the injunction is mandatory in form but the actual consequences of granting the specific relief sought, and the extent to which those consequences will cause irremediable prejudice to the respondent. A “higher degree of assurance” is necessary where, on the facts, complying with the mandatory order imposes significantly more prejudice if granted wrongly than if it were a prohibitory or final injunction.
I remind myself of the general guidance on interim injunctions contained in the decision of Chadwick J in Nottingham Building Society v. Eurodynamics Systems [1993] F.S.R. 468 at 474 and approved in Zockoll Group Ltd v Mercury Communications Ltd [1998] FSR 354 (Court of Appeal) that set out a four-point formulation:
Firstly, this being an interlocutory matter, the overriding consideration is which course is likely to involve the least risk of injustice if it turns out to be 'wrong' in the sense described by Hoffmann J.
Secondly, in considering whether to grant a mandatory injunction, the court must keep in mind that an order which requires a party to take some positive step at an interlocutory stage, may well carry a greater risk of injustice if it turns out to have been wrongly made than an order which merely prohibits action, thereby preserving the status quo.
Thirdly, it is legitimate, where a mandatory injunction is sought, to consider whether the court does feel a high degree of assurance that the plaintiff will be able to establish his right at a trial. That is because the greater the degree of assurance the plaintiff will ultimately establish his right, the less will be the risk of injustice if the injunction is granted.
But, finally, even where the court is unable to feel any high degree of assurance that the plaintiff will establish his right, there may still be circumstances in which it is appropriate to grant a mandatory injunction at an interlocutory stage. Those circumstances will exist where the risk of injustice if this injunction is refused sufficiently outweigh the risk of injustice if it is granted.
The principle to be applied from these authorities is as follows:
A mandatory injunction goes beyond preserving the status quo, and as it requires a party to take a positive step, there is a greater risk of injustice to the respondent if it is ultimately wrongly made.
It is necessary to consider the consequences of granting or refusing the injunction. If there is irremediable prejudice to the respondent, then the Court should firstly consider whether there is a “high degree of assurance” that the applicant will be able to establish its right, and that therefore the Order is unlikely to have been wrongly made.
If there is no “high degree of assurance”, then that is not an end to the matter. There are circumstances where the risk of injustice to the applicant if the injunction is refused is sufficiently great that it outweighs the risk of injustice if granted. In those circumstances, the high degree of assurance is not necessary.
The Court should therefore approach consideration of a mandatory interim injunction by considering the prejudice to the respondent, and if that prejudice is irremediable, then it should consider the degree of assurance that the order will not be “wrong” in the sense referred to by Hoffman in Olint. If there is a high degree of assurance, then that may well weigh in favour of making the order. If there is not, then it would it require a higher (and I would suggest a very high) risk of prejudice to the applicant, sufficient to outweigh the prejudice to the respondent.
Applying those principles to this Application:
I accept (as noted above) that there is a serious issue to be tried as to the extent of the Defendants’ repairing obligations including whether or not the obligation is to keep the roof weatherproof/watertight.
The evidence before me is that the roof is liable to a catastrophic failure, but that would not be prevented by the temporary works identified by the experts. Nevertheless, it remains a possibility in severe weather events.
Neither expert can say definitively that the roof is not weatherproof/watertight, although there is evidence of water ingress which may be the consequence of the failures of the roof and may be remedied by further repair work.
The cost of temporary works is likely to be in the region of somewhere between £0.5M to £1.2M (the Defendants’ expert’s costings are subject to the issue with the retrofitting of the fixings). It is clear from Mr Hopkinson’s report that the actual cost cannot be determined at this stage. The Claimants have provided a cross-undertaking in damages which has not been contested by the Defendants.
The proposed works by the Claimants’ expert are subject to several caveats (see above at §29). Further the Claimants’ expert identified issues with obtaining guarantees for the required 12–18-month period. He also noted that “…my recommendation would be to replace the roof coverings complete to the whole of the hangar roof, that any expenditure on temporary repairs would be better used to fund the replacement works and that I am unable to accept any responsibility for the implications of carrying out the suggested temporary repairs rather than replacing the roof coverings complete.”
The likely loss to the Claimants is poorly evidenced but at best appears to be well below that contended by Matthews 6 of £250k over a 2-year period.
The suggestion that the failure to grant the order sought might affect the Claimants’ accreditation with EASA and CAA is not supported by the evidence.
The prejudice to the Defendants of a mandatory order would be to require them to carry out extensive works to the Hangar roof (at substantial expense) which the experts are unable to say is currently not weatherproof/watertight. Those works are unlikely to do anything other than provide temporary protection and are subject to the above caveats about guarantees/fixings. Indeed, it is not certain that they would prevent water ingress, and the roof may be subject to total failure.
The prejudice to the Claimants is that there may be further incidents of water leaks over the next 12-18 months. However, the continuing problems with the roof are unlikely to result in significant losses, or to cause issues with the Claimants’ regulators. The evidence suggests that leaks have been dealt with by the Claimants by mitigating steps. Further, the occurrences suggest a rate of approx. 8 over a period of 9 months.
It is not certain that the work identified by the experts would fall within the repairing obligation on the Defendants pleaded by the Claimants – cf Particulars of Claim at §15.10:
“Repairing (and by way of repair, renewing, rebuilding and replacing), decorating, maintaining and cleaning the foundations, roof, structure and exterior of the Building [defined by cl. 1 as the Hangar] and all Common Parts and Conducting Media”
The Defendants’ acceptance of some obligations for repairing the roof (as evidenced in their defence and the works they contend have been carried out on an on-going basis) suggests that there is likely to be some obligation on them, but it may well not be as extensive as that asserted by the Claimants.
An obligation that the building is fit for purpose is not the same as “Repairing (and by way of repair, renewing, rebuilding and replacing”) covenant, and it cannot be said with a “high degree of assurance” that the Claimants will establish the right to require the Defendants to keep the roof “watertight and waterproof”.
Although the Claimants have sought to argue that the “exceptional” nature of an interim mandatory order to carry out repairs can be satisfied where there is a risk to an individual’s physical well-being, I am not satisfied that is applicable to this case. The quoted decision in Parker v Camden LBC states per Sir John Donaldson MR:
“However, I would accept that it is only in very rare cases that a mandatory injunction will be issued at an interlocutory stage. I would also accept, as Geoffrey Lane L.J. put it in Harold Stephen & Co. Ltd. v. Post Office [1977] 1 W.L.R. 1172, 1180:
"It can only be in very rare circumstances and in the most extreme circumstances that this court should interfere by way of mandatory injunction in the delicate mechanism of industrial disputes and industrial negotiations. It is likely, if mandatory injunctions are imposed in these circumstances, that more damage might be done than good, and the results are both unforeseeable and may be grave."
… We are faced with old people suffering very grave privations—the old and the very young are being exposed to a real risk of damage to health and even a very far from fanciful risk of death. In those circumstances, I would be extremely sorry to conclude that the courts could do nothing for them.
Per Browne-Wilkinson LJ
However, for the reasons that Sir John Donaldson M.R. has outlined, I think that this is truly an exceptional case in that we are talking about an undoubted breach of covenant giving rise to actual and immediate major discomfort and inconvenience and to a real risk of damage to health flowing from the admitted breach. It seems to me to be a wholly exceptional case in which a mandatory order could certainly be made.
In terms of the exercise of the discretion, it seems to me that there are, amongst others, these features which have to be weighed. In favour of making an order is the admitted breach by the local authority. Secondly, as I have said, the breach is causing severe hardship to the tenants, particularly to the elderly and young. There is sheltered housing involved. Thirdly, the breach is giving rise to an immediate fear as to the health of the tenants, going even to the risk of death.
There is no actual evidence of physical danger to the Claimants’ staff but in any case, any risk could be mitigated by the Claimants exercising their duties as occupier/employer.
Without a “high degree of assurance” that the Claimants will establish their right, the question is whether the risk of irremediable injustice to the Claimants if the order is not made sufficiently outweighs that to the Defendants if it is made. Although the costs of the work sought by the Claimants (in either form set out in the draft order) would be recoverable by the Defendants under the cross-undertaking in damages, that cannot in itself determine whether the Defendants have suffered irremediable prejudice – otherwise the existence of such an undertaking would determine the making of an injunction. Such an undertaking would only “bite” at the end of proceedings and in that time, the Defendants would be put to substantial expense solely to patch the roof pending the trial. That would be of irremediable prejudice to the Defendants.
Weighing the likely impact financially on the Claimants of continuing issues with water ingress, and the limitations on the proposed works suggested by the experts, I am not satisfied that the prejudice to the Claimants can be sufficient to outweigh that to the Defendants.
Conclusion
For the reasons set out above, I dismiss the Claimants’ application for a mandatory order for the repair of the Hangar roof. I would invite the parties to consider whether a draft Order can be agreed or whether a further hearing for any consequential matters is necessary. If the latter, then the parties should provide a time estimate, availability and a list of proposed issues to be considered.